Overhaul plan making method and system for power transmission equipment

A technology for maintenance planning and power transmission equipment, applied in the field of automation, can solve problems such as inaccurate calculation of maintenance planning results, and achieve the effects of good global search capability, high computing efficiency, and good convergence characteristics

Pending Publication Date: 2020-09-01
CHINA ELECTRIC POWER RES INST +2
View PDF0 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] Since maintenance plan optimization is a multi-objective, multi-constraint nonlinear combinatorial optimization problem, existing related algorithm research mainly focuses on Benders decomposition method and intelligent optimization algorithm. In recent years, intelligent optimization algorithm has been more and more widely applied to maintenance In the plan, typical heuristic search algorithms include genetic algorithm, particle swarm optimization algorithm, etc., but in the application scenarios with discrete variables, the results of calculation and maintenance plan obtained by genetic algorithm and particle swarm optimization algorithm are inaccurate

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Overhaul plan making method and system for power transmission equipment
  • Overhaul plan making method and system for power transmission equipment
  • Overhaul plan making method and system for power transmission equipment

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0063] Embodiment 1: as figure 1 As shown, the present invention provides a maintenance plan formulation method for power transmission equipment, including

[0064] S1 Obtain the construction period of each power transmission equipment and the power outage window period that can be arranged for maintenance;

[0065] S2 Bring the construction period of each power transmission equipment and the blackout window period that can be arranged for maintenance into the pre-built maintenance plan optimization model, and use the improved gravitational search algorithm to calculate, and obtain the maintenance time of each equipment;

[0066] S3 formulating a maintenance plan based on the maintenance time of each device;

[0067] The maintenance plan optimization model aims at the minimum power generation of abandoned renewable energy sources and the minimum distribution variance of the maintenance quantity, and is constructed with the grid's maintenance time requirements for each equipme...

Embodiment 2

[0151] Embodiment 2: Based on the same inventive concept, the present invention also provides a maintenance plan formulation system for power transmission equipment, including:

[0152] The obtaining module is used to obtain the construction period of each power transmission equipment and the power outage window period for arranging maintenance;

[0153] The calculation module is used to bring the construction period of each power transmission equipment and the power outage window period that can be arranged for maintenance into the pre-built maintenance plan optimization model, and use the improved gravitational search algorithm to perform calculations to obtain the maintenance time of each equipment;

[0154] Developing a module for formulating a maintenance plan based on the maintenance time of each device;

[0155] The maintenance plan optimization model aims at the minimum power generation of abandoned renewable energy sources and the minimum distribution variance of the ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an overhaul plan making method and system for power transmission equipment. The method comprises the following steps: obtaining the construction period of each power transmission equipment and a power failure window period capable of arranging overhaul; substituting the construction period of each power transmission device and the power failure window period capable of arranging overhaul into a pre-constructed overhaul plan optimization model, and performing calculation by utilizing an improved universal gravitation search algorithm to obtain overhaul time of each device; making an overhaul plan based on the overhaul time of each device, wherein the overhaul plan optimization model is constructed by taking minimum renewable energy power generation and minimum overhaul quantity distribution variance as targets and taking overhaul time requirements, power grid safety operation requirements and daily overhaul quantity requirements of the power grid for each deviceas constraints. The improved universal gravitation search algorithm based on the simulated annealing thought provided by the invention is suitable for solving the overhaul plan problem containing discrete variables, and the equipment overhaul time can be reasonably arranged.

Description

technical field [0001] The invention relates to automation technology, in particular to a method and system for formulating maintenance plans for power transmission equipment. Background technique [0002] According to the characteristics of the energy structure of each country, the distribution of energy supply and energy demand is reversed. The abundant clean energy such as wind power, photovoltaic and hydropower is mainly concentrated in areas far away from the load center. In order to achieve its effective consumption. For the preparation of power outage maintenance plans for high-voltage power transmission and transformation equipment (including 500kV and above voltage levels and some 220 / 330kV voltage levels of AC and DC lines and related busbars, main transformers and converters, etc.), guarantee The transmission and full consumption of renewable energy are the main factors that must be considered. [0003] Therefore, the main goal of transmission line maintenance p...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/00G06Q10/04G06Q10/06G06Q50/06
CPCG06Q10/04G06Q10/0637G06Q10/20G06Q50/06Y04S10/50
Inventor 蔡帜许丹戴赛崔晖丁强韩巍张加力李博刘芳燕京华闫翠会黄国栋张传成孙振李伟刚屈富敏韩彬盛灿辉胡晨旭杨占勇王伟
Owner CHINA ELECTRIC POWER RES INST
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products