BIM-based building decoration time consumption estimation system and analysis and prediction method
A technology for building decoration and data prediction, applied in the field of BIM building decoration, can solve the problems of time-consuming calculation of decoration, adjustment of construction period, delay of construction period, etc., to achieve the effect of accurate prediction results, avoid project delay, and speed up completion.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0050] This embodiment discloses as figure 1 A BIM-based building decoration time-consuming estimation system shown includes a display screen, a data acquisition module, a central processing unit, a data sorting module, a database, a data analysis module, a data prediction module, and an intelligent device; the display screen and the central The processor is connected in communication, the data acquisition module is connected in communication with the central processor, the data sorting module is connected in communication with the central processor, the central processor is connected in communication with a database, the database is connected in communication with the sorting module, the The data analysis module communicates with the data sorting module, the data prediction module communicates with the smart device, and the display screen is used to display the operation process of the data analysis module and the data prediction module.
[0051] The data acquisition module i...
Embodiment 2
[0058] This embodiment discloses a BIM-based architectural decoration time-consuming estimation and analysis method, including the following steps:
[0059] T1 obtains the data of completed engineering volume and total engineering volume, and obtains the unfinished engineering volume data L according to the total workload = completed workload + unfinished workload 未 = Li-li;
[0060] T2 obtains the data of the number of employees, time-consuming data and personal work efficiency data, and obtains the actual work efficiency of the individual according to workload = total work efficiency * working hours
[0061] T3 sets a personal work efficiency difference M, based on the personal actual work efficiency G in step 2 实 Get M=G 实 -Gi, and judge personal work efficiency according to the difference M of personal work efficiency;
[0062] T4 Obtain the first process, the second process, the time spent in the first process and the time spent in the second process, compare the tim...
Embodiment 3
[0074] This embodiment discloses a BIM-based method for estimating and predicting time-consuming architectural decoration, including the following steps:
[0075] S1 Obtain the actual work efficiency of the person, the total project quantity data, the specified completion time data and the number of employees, and obtain the estimated completion time according to the workload = total work efficiency * working time
[0076] S2 Compare the expected completion time in step 1 with the specified completion time data, and make a judgment based on the comparison result, specifically:
[0077] When T 预 >Wi, it is determined that the project will be delayed;
[0078] When T 预 =Wi, then it is determined that the project will be completed on time;
[0079] When T 预
[0080] S3 Select a remedial plan for the delayed project based on the above comparison results.
[0081] The selection of remedial schemes f...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com