Civil engineering construction method for quickly treating mudslide and landslide and collapse of mountains with weather-resistant woven bags
A landslide and civil engineering technology, which is applied in sea area engineering, water conservancy engineering, climate sustainability, etc., can solve problems such as unsuitable formless masonry, a large amount of labor, and long construction period
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0045] This embodiment 1 is illustrated in conjunction with a case in which a landslide surface height of 8 meters is caused by a debris flow caused by continuous days of torrential rain.
[0046] The construction object is a road landslide in a mountainous area. The vertical height of the landslide is 8 meters, the slope is 30 degrees, the transverse width is 50 meters, and the width is 5 meters. After the pre-construction inspection and engineering survey of the slope caused by the landslide caused by the debris flow, the measurement and calculation The amount of soil and rock is 2000 cubic meters, which is equivalent to the use of 2000 woven bags. The woven bags are products of the model KR-2BBL produced by Qingdao Pulin Packaging Products Co., Ltd.
[0047] The civil engineering construction method for rapid treatment of debris flow and landslide collapse by using weather-resistant woven bags is as follows:
[0048] 1. Construction plan:
[0049] The vertical height of th...
Embodiment 2
[0069] The construction object of this embodiment 2 is the roadbed washed away by the flood, the vertical height of the embankment of the roadbed is 6 meters, the slope is 30 degrees, the mold width is 10 meters, and the width is 7 meters. After the pre-construction inspection and engineering survey of the slope, the measured and calculated soil and rock volume is 280 cubic meters, which is equivalent to 420 woven bags.
[0070] The main steps of the construction method of the present embodiment 2 are the same as those of the embodiment 1, except that the earth and stone packed in the woven bags are sandstones, and the piled height of the woven bags is 6 layers.
Embodiment 3
[0072] The construction object of this embodiment 3 is a landslide caused by heavy rain for many days, and the earth and gravel of the landslide fills the road. The vertical height of the slope bank of the road is 10 meters, the slope is 30 degrees, the transverse width is 30 meters, and the width is 7 meters. After the pre-construction inspection and engineering survey of the slope, the measured and calculated earth and rock volume is 2100 cubic meters, which is equivalent to the consumption of 2100 woven bags.
[0073] The main steps of the construction method of this embodiment 2 are the same as those of embodiment 1, except that the soil and rock packed in the woven bag is a mixture of soil and sand produced by landslides, and the stacking height of the woven bag is 10 layers.
[0074] Compared with the prior art, the construction method of the present invention is simple, the working area required by the working site is small, the secondary damage to the environment is sma...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com