Construction method of planting orychophragmus violaceus in saline-alkali land greening protection slope
A construction method, the technology of Zhuge Cai, applied in the construction field of saline-alkali land greening and slope protection, can solve the problems of single vegetation, low survival rate, and reduction of alkali return in saline-alkali land slope protection, and achieve low survival rate, single vegetation, and reduction of alkali return The effect of the phenomenon
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0054] A construction method for greening slope protection on saline-alkali land for planting Zhuge vegetable, comprising the following steps:
[0055] (1) Slope cleaning
[0056] Remove plants, silt, floating soil, pumice and protruding rocks on the slope, loosen and rake the ground;
[0057] (2) Soil improvement;
[0058] (3), configure green concrete
[0059] Prepare the greening concrete, the greening concrete includes base concrete and surface concrete, the porosity of the base is greater than that of the surface;
[0060] (4), pouring
[0061] On-site pouring of the base layer on the slope, the surface is flattened by formwork or short-term vibration, the film is covered for maintenance and anchors are set, and the film is removed after 4 days and the surface layer is poured in the same way to obtain the initial slope protection;
[0062] (5), sowing slope pretreatment
[0063] Sprinkle water on the surface of the initial slope protection, and then spray a layer of ...
Embodiment 2
[0097] A construction method for greening slope protection on saline-alkali land for planting Zhuge vegetable, comprising the following steps:
[0098] (1) Slope cleaning
[0099] Remove plants, silt, floating soil, pumice and protruding rocks on the slope, loosen and rake the ground;
[0100] (2) Soil improvement;
[0101] (3), configure green concrete
[0102]Prepare the greening concrete, the greening concrete includes base concrete and surface concrete, the porosity of the base is greater than that of the surface;
[0103] (4), pouring
[0104] On-site pouring of the base layer on the slope, flattening the surface with formwork or short-term vibration, covering the film for maintenance and setting anchor rods, removing the film after 4 to 5 days and pouring the surface layer in the same way to obtain the initial slope protection;
[0105] (5), sowing slope pretreatment
[0106] Sprinkle water on the surface of the initial slope protection, and then spray a layer of nu...
Embodiment 3
[0141] A construction method for greening slope protection on saline-alkali land for planting Zhuge vegetable, comprising the following steps:
[0142] (1) Slope cleaning
[0143] Remove plants, silt, floating soil, pumice and protruding rocks on the slope, loosen and rake the ground;
[0144] (2) Soil improvement;
[0145] (3), configure green concrete
[0146] Prepare the greening concrete, the greening concrete includes base concrete and surface concrete, the porosity of the base is greater than that of the surface;
[0147] (4), pouring
[0148] On-site pouring of the base layer on the slope, the surface is flattened by formwork or short-term vibration, the film is covered for maintenance and anchors are set, and the film is removed after 4 days and the surface layer is poured in the same way to obtain the initial slope protection;
[0149] (5), sowing slope pretreatment
[0150] Sprinkle water on the surface of the initial slope protection, and then spray a layer of ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com