Construction progress prediction method and system based on BIM model

A construction progress and model technology, applied in the field of substation construction management informatization, can solve problems such as prolonging the construction period, occupying time, unfavorable construction progress on time, etc., and achieve the effect of increasing reliability assurance, reducing complexity and increasing convenience

Inactive Publication Date: 2017-12-15
JIAXING HENGCHUANG ELECTRIC POWER DESIGN & RES INST CO LTD +1
View PDF6 Cites 25 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] In the prior art, although there are some substation construction progress management methods, these methods are all customized solutions for a specific project. The scheme can only reflect the project itself, and there are many ground equipment and accessories in the substation site. The quality requirements for the construction process are also high. The existing substation construction progress management method cannot combine the actual substation construction situation to predict the problems in the substation construction. After understanding the root of the problem, organize an expert group to find a preliminary solution to the problem, and take measures to deal with the problem according to the plan. The period between the discovery of the problem and the solution to the problem takes up the time in the construction plan and prolongs the construction period. The construction period is not conducive to the timely advancement of the construction progress

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction progress prediction method and system based on BIM model
  • Construction progress prediction method and system based on BIM model
  • Construction progress prediction method and system based on BIM model

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0058] Combining the above-mentioned inventive idea of ​​the technical solution of the present invention, a method for predicting the construction progress based on the BIM model, such as figure 1 shown, including:

[0059] Step S100: Obtain construction information to build a three-level model, which includes a macro model of the overall project, a meso model of ancillary buildings, and a micro model of equipment lines.

[0060] According to the content of the substation project, all the construction information related to the project is obtained, and these information are imported into the BIM system to establish the project model. The information is divided into first to third model data according to the level of refinement of the information content. The first model data includes the 3D model of the substation project, the overall construction progress and engineering information. In this modeling, different materials and colors are used to represent each area, walls, roa...

Embodiment 2

[0083] Combining the above-mentioned inventive idea of ​​the technical solution of the present invention, a system for predicting the construction progress based on the BIM model, such as Image 6 shown, including:

[0084] The acquiring unit 100 is configured to acquire construction information.

[0085] The construction unit 200 is configured to construct and save a three-level model according to the construction information. The three-level model includes a macro model of the overall project, a meso model of ancillary buildings, and a micro model of equipment lines.

[0086] The preparation unit 300 is used to prepare the construction progress plan. Such as Figure 7 As shown, the compilation unit 300 includes a creation subunit 301 , a corresponding subunit 302 and a formulation subunit 303 .

[0087] The creating subunit 301 is used to obtain schedule task arrangement and create engineering task.

[0088] The corresponding subunit 302 is used for corresponding the sch...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction progress prediction method and system based on a BIM model. The method comprises the steps of obtaining construction information so as to construct a triple-level model, and the triple-level model comprises a macro model, a meso model and a micro model; establishing a construction progress plan, and linking the construction progress and the triple-level model so as to generate four-dimensional progress simulation; according to four-dimensional progress simulation, building a construction task decomposition structure so as to formulate construction plans of different levels, according to the project content, adding construction tasks and progress plans step by step into the construction plan to form a four-dimensional construction simulation model; according to the four-dimensional construction simulation model, guiding the progress construction progress, displaying each work of the construction process in the visualized object building component virtual building process, adding the time dimension, and on the basis of real-time mathematical statistical analysis, simulating the problem in the construction process; from macroscopic to mesopic, and then microscopic substep modeling is performed, different-level models can be switched through clicking operations, and convenience is greatly improved.

Description

technical field [0001] The invention relates to the technical field of substation construction management information technology, and more specifically, it relates to a method and system for predicting construction progress based on a BIM model. Background technique [0002] As an important part of the power system, the substation is an important hub connecting many remote areas or special operation areas. Due to its own particularity, the construction of the substation is different from the difficulty of ordinary building construction, and its construction efficiency is also higher than that of ordinary buildings. The construction efficiency of ordinary building construction is low, and the utilization rate of materials is low. Among them, 27% of the construction process needs to be reworked, 62% of the labor force is wasted, and 9% of the loss comes from the waste of materials. The construction progress management of substation construction projects is an important link i...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06F17/50G06Q10/06G06Q50/06
CPCG06F30/13G06Q10/067G06Q50/06
Inventor 陈鼎仇群辉莫加杰陆恩灏沙磊何平陈兵强陈杰光靳雅超宋同
Owner JIAXING HENGCHUANG ELECTRIC POWER DESIGN & RES INST CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products