Treatment method for domestic waste yard
A garbage dump, living technology, applied in the field of domestic garbage dump management
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0019] The governance method proceeds as follows:
[0020] a. Level the surface of the domestic waste dump with bulldozing equipment;
[0021] b. Starting from the periphery of the surface layer facing the direction opposite to the water outlet port, use a core drill belt with a diameter of 0.1 m. The air compressor drills vertical holes from top to bottom, and the pressure from the air compressor while drilling is 8Kg / cm 2 The gas presses out the water in the domestic garbage around the drilling hole and blows out the gaps. When drilling to the bottom of the domestic garbage dump, add cement in the proportion of cement: sand = 1:2 parts by weight to the gas from the air compressor Mortar, add cement accelerator to the cement mortar according to 4 / 10,000 of the weight of cement and sand. With the pouring of cement mortar, the core drill is gradually lifted to the surface of the domestic garbage dump, and the drilling and grouting is completed; the hole spacing is 8 meters and...
Embodiment 2
[0026] The governance method proceeds as follows:
[0027] a. Level the surface of the domestic waste dump with bulldozing equipment;
[0028] b. From the periphery of the surface facing the direction opposite to the water outlet port, use a core drill with a diameter of 0.3 meters to drill vertical holes from top to bottom with an air compressor, and the pressure from the air compressor while drilling is 3Kg / cm 2 The gas presses out the water in the domestic garbage around the drilling hole and blows out the gaps. When drilling to the bottom of the domestic garbage dump, add cement in the proportion of cement: sand = 1:3 parts by weight to the gas from the air compressor Mortar, add cement accelerator to the cement mortar according to 4 / 10,000 of the weight of cement and sand. With the pouring of cement mortar, the core drill is gradually lifted to the surface layer of the domestic garbage dump, and the drilling and grouting is completed; the hole spacing is 4 meters and gra...
Embodiment 3
[0033] The governance method proceeds as follows:
[0034] a. Level the surface of the domestic waste dump with bulldozing equipment;
[0035] b. From the periphery of the surface facing the direction opposite to the water outlet port, use a core drill with a diameter of 0.2 meters to drill vertical holes from top to bottom with an air compressor, and the pressure from the air compressor while drilling is 5Kg / cm 2 The gas presses out the water in the domestic garbage around the drilling hole and blows out the gaps. When drilling to the bottom of the domestic garbage dump, add cement in the proportion of cement: sand = 1:2.5 parts by weight to the gas from the air compressor Mortar, add cement accelerator to the cement mortar according to 4 / 10,000 of the weight of cement and sand. With the pouring of cement mortar, the core drill is gradually lifted to the surface layer of the domestic garbage dump, and the drilling and grouting is completed; the hole spacing is 6 meters and g...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com