Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Circuit tower-foundation flow-style mechanical construction method

A mechanical construction and flow-through technology, which is applied in the direction of foundation structure engineering, construction, sheet pile walls, etc., can solve the problems of poor pile quality of the foundation as a whole, large amount of labor for self-mixing concrete, collapse of holes, etc., and achieve increased pile side friction Effects of resistance, construction site cleanliness, and hole-forming quality improvement

Inactive Publication Date: 2017-06-09
高歌
View PDF5 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] At present, during the foundation construction of transmission lines, the common operation method is to use rotary drilling rigs or submersible drilling rigs to drill holes, weld steel bars on site, manually hang and place reinforcement cages, and use self-mixing concrete for manual pouring. This operation method has the advantages of The following disadvantages: 1. The drilling efficiency of the rotary drilling rig is low, the self-mixing concrete requires a large amount of labor, the pouring efficiency is low, and the serial operation method is adopted. The previous process is not completed, and the next process cannot be carried out. frame, the drilling rig cannot be transferred to the construction site, resulting in low efficiency of the overall foundation construction and a large amount of labor
2. On-site welding needs to invest in temporary electrical devices, and the safety risk of manual lifting of the steel cage is relatively high
3. The quality of the hole formed by the rotary drilling rig is poor, and it is prone to eccentricity and hole collapse, and the verticality of the pile cannot be guaranteed. It is difficult to ensure the quality of the concrete pouring by mixing and pouring on site, resulting in poor quality of the overall foundation pile
4. The traditional line foundation construction method requires a lot of labor input. With the increasing labor cost, the economic benefit is poor

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Circuit tower-foundation flow-style mechanical construction method
  • Circuit tower-foundation flow-style mechanical construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0031] The concrete implementation steps of a kind of line tower base flow-type mechanical construction method are:

[0032] 1. Temporary road construction:

[0033] (1) According to the mechanized construction characteristics of the line foundation, select a rotary drilling rig with a maximum torque of 80-150 as the drilling machine, and use the length, width, tonnage, and turning radius of the rotary drilling rig to compare the width, turning radius, and foundation of the entry and exit roads Bearing capacity requirements as temporary road construction standards;

[0034] (2) Use excavators and bulldozers to widen, fill and level the road; use road rollers to harden the road, and then lay steel plates with a thickness of more than 50mm on the road; at the same time, use 6m*1.5m*50mm steel plates on the working surface The foot is laid in a ring, and the overlapping position of the steel plate and the steel plate is connected by spot welding with a short steel bar head and a...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

Provided is a circuit tower-foundation flow-style mechanical construction method. The method includes the follow stepsthat 1, temporary roads are constructed; 2, early-stage preparation of construction is made; 3, arotary drilling rig conducts pore forming; 4, a steel reinforcement cage conducts industrialized processing and installation; 5, commercial concrete is used for pouring; 6, mechanical equipment is maintained; according to the circuit tower-foundation flow-style mechanical construction method, an operation mode whereparallel operation is combined with modularizedconnection is adopted, and the purposes of mechanical construction and flow-style operation in the overall process of the circuit tower foundation are achieved; fully mechanical constructionis adopted, and the temporary power input and the workload of manual operation are reduced;machines replace manpower to complete the lifting and lowering of the rotary drilling rig and other high-risk construction processes, dynamic risk values are reduced, and security risks are reduced; besides, construction sites are clean and tidy, and environmental pollution is less; meanwhile, the vibration of the rotary drilling rig is slight, the noise is low, so that the rotary drilling rig does not cause noise pollution to environment.

Description

technical field [0001] The invention relates to the field of foundation construction of overhead power transmission lines, in particular to a flow-type mechanical construction method for line tower foundations. Background technique [0002] At present, during the foundation construction of transmission lines, the common operation method is to use rotary drilling rigs or submersible drilling rigs to drill holes, weld steel bars on site, manually hang and place reinforcement cages, and use self-mixing concrete for manual pouring. This operation method has the advantages of The following disadvantages: 1. The drilling efficiency of the rotary drilling rig is low, the self-mixing concrete requires a large amount of labor, the pouring efficiency is low, and the serial operation method is adopted. The previous process is not completed, and the next process cannot be carried out. Without the frame, the drilling rig cannot be transferred to the construction site, resulting in low ef...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D5/38E02D15/04
CPCE02D5/38E02D15/04
Inventor 高歌
Owner 高歌
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products