Construction method of inner excavated abutment

A construction method and abutment technology, applied in excavation, earthwork drilling, infrastructure engineering and other directions, can solve the problems of large construction site, large excavation height, slipping and other problems, and achieve the effect of small construction site and ensuring construction safety.

Active Publication Date: 2017-05-24
中铁十九局集团华东工程有限公司 +1
View PDF6 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] At present, the construction of the abutment at the exit of the tunnel is to excavate the abutment to the bottom of the tunnel at one time. The excavation height is large and the construction site is large. If the side slope is loose, it will cause slipping and collapse, which poses a safety hazard.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0022] For the construction method of excavating the inner abutment, firstly, the dangerous rocks on the outer side slope of the tunnel are manually removed, the side slope is temporarily supported (back pressure, filling joints and anchor spraying support), the loose bodies on the outer side slope of the tunnel are cleaned, and the foundation trench is opened. Excavation (excavation to the bottom of the cap), construction of excavated piles, construction of the cap, construction of the platform body, permanent support of the slope (grid beam anchor cable).

[0023] The specific construction method is:

[0024] 1. First, clean up the dangerous rocks on the slope outside the tunnel, and then seal them with plain spraying C25 concrete, with a spraying thickness of 8cm;

[0025] 2. Bolt and shotcrete support is carried out on the outer slope of the tunnel from top to bottom. The anchor rod adopts φ22mm mortar anchor rod. The length of the mortar anchor rod is 4.5m. Net, the grid...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a construction method of an inner excavated abutment in tunnel construction. The method mainly solves the problems of sliding slope caused by big excavation height and loose slope of the inner abutment at the tunnel outlet at present. The method includes steps of removing collapse rocks at heading slope of outside of a tunnel, performing anchor-plate retaining on the outside slope of the tunnel from top to bottom; applying lock pin anchor pipes at two lining parts of both sides of the abutment and the front abutment beam groove; arranging temporary supports to left and right side walls of two liners of the tunnel, and excavating the abutment construction in the tunnel step by step, and excavating left part and then right part; applying the excavation scheme of concrete protecting wall to a hole excavating pipe, and excavating segmentally, and excavating one segment and supporting the segment; after excavating to a design elevation, placing a reinforcement cage, and pouring concrete; pouring a cushion cap concrete once, arranging face protecting ribs at four sides of the cushion cap; pouring the abutment body concrete twice, wherein the first pouring height is bottom height of a cushion, and the second pouring height is the designed elevation. The method is small in construction site, and segmental construction is free from slide collapse.

Description

[0001] Technical field: [0002] The invention relates to an excavated inner abutment construction method in tunnel construction. [0003] Background technique: [0004] At present, the construction of the abutment at the exit of the tunnel is to excavate the abutment to the bottom of the tunnel at one time. The excavation height is large, and the construction site is large. If the side slope is loose, it will cause slipping and collapse, which poses a safety hazard. [0005] Invention content: [0006] The technical problem to be solved by the present invention is to provide an excavated inner abutment construction method with small construction site, no sliding and collapse phenomenon, and safe construction. [0007] The above purpose is achieved in this way: the construction method of excavating the inner abutment first manually removes the dangerous rocks on the outer side slope of the tunnel, temporarily supports the side slope (back pressure, filling joints and anchor sp...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/00E21D9/14E21D11/14E21D20/02E21D11/10E02D17/20E02D17/00
CPCE02D17/00E02D17/20E21D9/00E21D9/14E21D11/10E21D11/102E21D11/107E21D11/14E21D20/021
Inventor 王志科李野秦殿明宋海丰李向光刘百合任岗
Owner 中铁十九局集团华东工程有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products