A method for ensuring the traffic of the main road during the reconstruction and expansion construction period of the expressway

A technology in the expressway and construction period, which is applied in the direction of roads, roads, buildings, etc., can solve the problems of reducing service levels, affecting driving safety, connecting urban traffic with expressways, and short distances before and after temporary opening areas, so as to avoid construction dead ends and engineering Effects with clear meaning and simple operation

Inactive Publication Date: 2017-06-30
山东高速工程咨询集团有限公司 +2
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Traffic protection during reconstruction and expansion construction is a very difficult issue. From the perspectives of improving construction progress and ensuring construction safety, it is the most reliable to close the entire section of the existing expressway for construction; but from the perspective of ensuring that the expressway provides a convenient way for people to travel, From the perspective of not affecting the normal operation of major urban economies, during the reconstruction and expansion construction period, it is necessary not to significantly reduce the service level but to keep the expressway unobstructed; Road managers are almost unacceptable
[0003] In previous expressway reconstruction and expansion projects, due to the inoperability of the traffic protection plan, many of the traffic protection plans scheduled at the beginning of the construction could not be implemented, and measures such as long-distance two-way two-lane traffic, forced diversion, and even closed construction of sections had to be taken. , such as the Beijing-Shibai Expressway, etc., have seriously affected the driving safety and construction safety during the construction period and the traffic between the cities connected by the expressway
Utilizing the opening of the original central divider or adding temporary openings in the central divider to achieve alternate traffic openings on the left and right sides is a common solution. If one or two temporary openings are set in the central divider, the area around the temporary openings cannot be solved when the left and right sides are opened to traffic alternately. In order to deal with the problem of old road disease and widening on both sides, in order to deal with this area, most of the temporary sidewalks are paved, and the vehicles drive slowly through the sidewalks. In addition, the distance between the front and rear of the temporary opening area is short, which is not conducive to ensuring construction quality and construction safety.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A method for ensuring the traffic of the main road during the reconstruction and expansion construction period of the expressway
  • A method for ensuring the traffic of the main road during the reconstruction and expansion construction period of the expressway
  • A method for ensuring the traffic of the main road during the reconstruction and expansion construction period of the expressway

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0038] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments, but the present invention is not limited to these embodiments.

[0039] Such as Figure 1 to Figure 8 As shown in the figure, a method for ensuring the traffic of the main road during the reconstruction and expansion construction period of the expressway, the method includes the determination of the number of temporary openings in the central divider, the selection of the positions of the temporary openings, the determination of the distance between the temporary openings, and the conversion and opening of the temporary openings And the series of processes of alternate construction of the left and right sides, specifically including the following steps:

[0040] Step 1: Divide the construction section of the incoming lane 3 and the outgoing lane 5 on both sides of the central divider on the expressway. For the convenience of description...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a method for ensuring the traffic of main roads during the reconstruction and expansion construction period of an expressway. In the method, three temporary openings are continuously opened in one place of the central divider, and the length of the construction sections A and B of the expressway to be expanded is determined. Alternate division, after the initial construction of A section to the lower layer of the road surface, the vehicles drive into B section through the temporary opening of the central divider, and change the position of the temporary opening according to the construction progress, creating a working surface for the alternate construction of A and B sections, and Realize full-time two-way four-lane guaranteed traffic. The method has clear engineering significance and simple operation, and can be used to ensure the traffic of two-way four-lane highways on the main line during the reconstruction and expansion of two-way four-lane highways into two-way eight-lane or more construction.

Description

technical field [0001] The invention relates to a method for ensuring the traffic of main line roads during the reconstruction and expansion construction period of an expressway, and is particularly suitable for the traffic protection of the main line with two directions and four lanes during the reconstruction and expansion of the original two-way four-lane high-speed highway into a two-way expressway with more than eight lanes. Background technique [0002] From the 1990s to the beginning of this century, most of the expressways built in my country were two-way four-lane. With the development of the national economy and the improvement of people's living standards, the traffic flow on the expressway has increased significantly, resulting in a gradual decrease in its service level. Some projects have been done domestically to transform 4 lanes into two-way 8-lane or even two-way 10-lane. Traffic protection during reconstruction and expansion construction is a very difficult ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E01C1/00
Inventor 郭保林孙日双潘希峰宋亚伟赵永伟张曦黄大伟李文静魏家旭刘睿迪
Owner 山东高速工程咨询集团有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products