Resource Balance Adaptive Scheduling Method in Multi-project and Multi-task Management

A resource balancing and scheduling method technology, applied in the field of project management, can solve the problems that cannot meet the actual needs of project management implementation and customers, and tasks cannot be cut from the start time of tasks, so as to improve project quality and project progress and reduce project costs. Cost, effect of improving project quality

Active Publication Date: 2016-10-26
CHENGDU XIMENG TEKE TECH DEV CO LTD
View PDF4 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] Various heuristic algorithms for quick processing methods when fewer resources are overloaded, when FS (finish-start), SS (start-start), SF (start-finish), FF (finish-finish) How to quickly determine the task priority relationship when the connection relationship appears at the same time and the tasks are many-to-many relationships, as well as task deployment conditions, task duration restrictions (including parent task duration restrictions), tasks that cannot be cut, whether the task start time is advanced, and tasks that cannot Practical issues such as how to deal with scheduling balance and how to deal with the constraint relationship between projects have not been dealt with, which cannot meet the actual needs of project management implementation and the actual needs of customers

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0019] The resource balance adaptive scheduling method in the multi-project and multi-task management of the embodiment of the present invention specifically includes the following steps:

[0020] S1. Resource pool resource replacement: find out the overloaded resources in the system resources that participate in leaf node tasks and are in an incomplete state, and obtain their replacement conditions: participate in tasks to be deployed (such as creation or assignment), resource characteristics (such as resource pool relationships) , skill requirements), resource demand (such as working day requirements), find resources that meet the replacement conditions through the resource pool, and then judge whether the task requirement is overloaded within the duration of the task according to the upper limit of its load. When there is no overload and the replacement balances all the resources to be deployed When the resource of the task is overloaded, the resource is replaced, and the re...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a resource balance self-adaptive scheduling method in multi-project and multi-task management. The method of the invention combines the actual needs of customers and the actual problems of project management, and satisfies the requirements of each item in the project when the parallel resources of a single project or multiple projects are overloaded. According to various practical constraints, while automatically balancing and allocating resources, reasonable scheduling and arrangement of project progress are made, resources are rationally utilized, and project quality is improved, which effectively solves the problem of project scheduling under various complex constraints in the actual project management implementation, and quickly and automatically realizes resources. The balanced utilization of the project generates a reasonable project schedule, which effectively reduces the project cost and project risk, improves the project quality and project progress, and increases the project benefit.

Description

technical field [0001] The invention belongs to the technical field of project management, and in particular relates to a resource balance self-adaptive scheduling method in multi-project and multi-task management under complex constraint conditions. Background technique [0002] In the actual implementation of project management, whether it is a single project or multiple projects in parallel, resources such as labor, materials, equipment, etc. are one of the very important constraints, and these resources are not unlimited supply, and resource constraints lead to excessive resources in the project. When loading, under the premise of satisfying other constraints such as overlapping tasks in the project, the resources are balanced and fully utilized, the project schedule is reliably and reasonably arranged, and the construction period is the shortest. [0003] The traditional critical path method (Critical Path Method, CPM) and plan review method (Plan Evaluation and Review ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): G06F17/00
Inventor 高智伟张源
Owner CHENGDU XIMENG TEKE TECH DEV CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products