Construction method of shear wall and column formwork for main structure

A main structure and shear wall technology, applied in building construction, building material processing, construction, etc., can solve the problems of prolonged construction period and difficult control of concrete quality, shortening construction period, saving construction period and human resources, shortening The effect of construction period

Inactive Publication Date: 2016-03-30
JIANGNAN CONSTR CO LTD DONGYANG ZHEJIANG
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] With the continuous development of urban construction, there are more and more small high-rise buildings and high-rise buildings. The short-leg shear wall column-frame shear system is widely used in the design. According to the traditional construction method, the shear wall and column are poured first. The post-cast beam floor concrete construction method is difficult to control the quality of the concrete at the wall, column-beam joints, and the construction period is prolonged

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of shear wall and column formwork for main structure

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0029] The construction method of the short-leg shear wall and column formwork construction technology in the main structure after the beam slab, taking the construction technology of the main structure of the 2# building in a certain garden in Wuxue, Hubei as an example, for the short-limb shear wall of the present invention, the column frame The various organizational links of the construction of the main structure of the shear system are comprehensively described. Construction process flow chart see figure 1 .

[0030] 1. Construction preparation steel bar processing

[0031] 1) Do a good job of site layout and site hardening.

[0032] 2) Pile up short-limb shear walls, columns, beams, and slab steel bars prepared on site according to specifications.

[0033] 2. Construction preparation formwork processing

[0034] 1) Selection of formwork materials for short-leg shear walls, columns and beams, and floor slabs:

[0035] a. In the short-limb shear wall and column-frame ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The present invention relates to a construction method of beam slab first and then short limb shear wall and column formwork for the main structure. The method is constructed in sequence according to the following steps: a. Binding the short limb shear wall and column reinforcement; b. Installing the beam slab formwork; c. Binding beams and floor reinforcements: Before binding beams and reinforcements, the shear walls and column reinforcements must be corrected. Immediately after the beam reinforcements are bound, check and accept them, and then bind the floor reinforcements; d. Install the short-leg shear walls while binding the floor reinforcements , column formwork; e, pouring concrete: beams, floors, short-leg shear walls, and column concrete are poured at the same time. The invention enables the installation of the short-limb shear wall and column formwork and the binding of beams and floor steel bars that are not on the same working surface at the same time, so that the installation of the short-limb shear wall and column formwork changes from a key task to a non-critical work. It does not occupy the construction period, which shortens the construction duration of the main frame-shear structure main project, and greatly shortens the construction period of the main structure and the time interval for labor to stop working.

Description

technical field [0001] The invention belongs to the field of building construction, and in particular relates to a construction method of a beam slab first and then a short limb shear wall and a column formwork for a main structure. Background technique [0002] With the continuous development of urban construction, there are more and more small high-rise buildings and high-rise buildings. The short-leg shear wall column frame shear system is widely used in the design. According to the traditional construction method, the shear wall and column are poured first. The post-cast beam floor concrete construction method is difficult to control the quality of the concrete at the joints of walls, columns and beams, and the construction period is prolonged. [0003] Install the formwork according to the conventional method, and the construction sequence of the main structure of the short-limb shear wall and column is generally: binding the steel bars of the short-limb shear wall colu...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E04G21/00
Inventor 刘强张正天包宁军
Owner JIANGNAN CONSTR CO LTD DONGYANG ZHEJIANG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products