High-permeability zone under-water-level elevator foundation pit open caisson moulding bed construction method
A construction method and high-penetration technology, which can be used in infrastructure engineering, caisson, construction, etc., and can solve problems such as increased cost and great construction difficulty.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0110] A method for constructing an elevator foundation pit caisson tire formwork under the water level of a high-permeable layer, comprising the following steps:
[0111] (1) Positioning and setting out of the foundation trench, and leveling the bottom plate of the foundation pit
[0112] (1) Arrangement of measurement control network: the measurement control points of the center line and elevation of the caisson shall be set in advance on the site as the basis for caisson positioning and setting out and sinking observation;
[0113] (2) Level the bottom plate according to the position of the caisson determined in the construction plan, release the control line of the caisson position, use sand, sleepers, and 100mm thick C10 concrete cushion for the bottom of the caisson bottom, and use a tamping machine to tamp and plate The vibrator is vibrated; the skids are laid at a distance of 320mm, arranged vertically according to the direction of the center of the circle, and coarse ...
PUM
Property | Measurement | Unit |
---|---|---|
Thickness | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com