Embodiment 1
[0022] 1) Manufacturing foot protection: make gabion foot protection at the lower edge of the planned stone dumping area, with a foot protection width of 1 meter or more;
[0023] 2) Stone dumping: first throw a large stone foundation (block diameter 20-30 cm), then throw small stones for leveling (block diameter 10-20 cm), and the total thickness of the stone dump layer is 30-60 cm;
[0024] 3) Paving planting soil: Pave geotextile on the riprap layer, and then spread planting soil more than 30cm thick;
[0025] 4) Plant establishment: sowing amorpha ( Amorpha fruticosa ), Buddleia ( Buddleja lindleyana) seed;
[0026] 5) Covering: Covering a layer of gravel with a thickness of 10cm. The gravel layer is composed of coarse sand with a particle size of 0.5-2mm and gravel with a particle size of 2-4.75mm, with a volume ratio of 1:1.
[0027]
Embodiment 2
[0029] 1) Manufacturing foot guards: make dry block stone foot guards at the lower edge of the planned rock dumping area, with a foot guard width of more than 1 meter;
[0030] 2) Stone dumping: first throw a large stone foundation (block diameter 20-30 cm), then throw small stones for leveling (block diameter 10-20 cm), and the total thickness of the stone dump layer is 30-60 cm;
[0031] 3) Paving planting soil: Lay geotextile on the riprap layer, and then spread planting soil more than 20cm thick;
[0032] 4) Plant establishment: sowing Lespedeza ( Lespedeza bicolor )seed;
[0033] 5) Covering: Covering a 5cm thick gravel layer. The gravel layer is composed of coarse sand with a particle size of 0.5-2mm and gravel with a particle size of 2-4.75mm. The volume ratio of the two is 1:2.
Embodiment 3
[0035] 1) Manufacture of foot guards: use mortar block stones as foot guards on the lower edge of the planned rubble area. The width of the foot guards is more than 1 meter and the height is slightly larger than the thickness of the rubble layer;
[0036] 2) Rock dumping: first throw a large stone foundation (block diameter 20-30 cm), then throw small stones for leveling (block diameter 10-20 cm), and the thickness of the dumped rock layer is 30-60 cm;
[0037] 3) Paving planting soil: Pave geotextile on the riprap layer, and then spread planting soil more than 30cm thick;
[0038] 4) Plant establishment: planting water bayberry ( Adina rubella ), sowing bermudagrass ( Cynodon dactylon )seed;
[0039] 5) Covering: Covering a 5-15cm thick gravel layer. The gravel layer is composed of coarse sand with a particle size of 0.5-2mm and gravel with a particle size of 2-4.75mm. The volume ratio of the two can be 1:1~1:2;
[0040] As time goes by, under the action of flowing water, the upper ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com