Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Method for building sea filling embankment

A sea embankment and embankment technology, which is applied in the field of urban road embankment engineering construction, can solve the problems of slow construction progress, large working area, and difficulty in meeting the construction progress, so as to reduce the amount of silt engineering, shorten the construction time, project cost and economic benefits obvious effect

Active Publication Date: 2011-07-06
DALIAN MUNICIPAL DESIGN & RES INST
View PDF6 Cites 23 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] When the road crosses the seaside shoal or there is a thick silt layer under the water, the embankment is usually constructed by mechanically removing the silt and replacing it. However, this method requires a large excavation area, resulting in a slow construction progress. Difficult to meet construction progress requirements under tight construction schedule
[0004] The commonly used method when building coastal roads in Dalian area to cross the soft ground—excavation and replacement, requires dredgers to remove all the silt in the embankment area that needs to be cleared, and the underwater silt has a relatively large fluidity, especially when dredgers are working The disturbance of the underwater silt enhances the fluidity of the underwater silt, the water area and the underwater influence area are very large, and the amount of silt removal increases at the same time

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for building sea filling embankment
  • Method for building sea filling embankment
  • Method for building sea filling embankment

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0078] The present invention will be further described below in conjunction with accompanying drawing. Such as Figure 1-5 Shown, a kind of construction method of reclamation embankment comprises the following steps:

[0079] A. Select bearing layer: According to geological data, load and use requirements, apply embankment stability and settlement calculation results to select bearing layer;

[0080] B. Select embankment section: Use embankment stability calculation and slope protection form to determine embankment section, especially for coastal embankment due to wave action, intertidal zone slope protection, underwater platform and wave load, rationally select slope protection form and embankment slope Foot outer platform width;

[0081] C. Determine throwing and filling parameters: The throwing and filling parameters include the height and width of embankment body throwing and filling. The design section of the dike body, the thickness of the silt 17 and its strength ind...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Lengthaaaaaaaaaa
Lengthaaaaaaaaaa
Login to View More

Abstract

The invention discloses a method for building a sea filling embankment. The method comprises the following steps: a bearing stratum is selected; an embankment cross section is selected; throw-filling parameters are determined; explosion parameters are determined; and embankment body throw-filling, embankment head explosion-filling, embankment top supplement-filling and embankment side explosion-filling are implemented. The method of silt squeezing and rock filling by blasting disclosed by the invention is conducted in a manner that explosive groups are buried and placed in a muddy soft foundation with a certain distance and depth from the outer edge of a rock body, a cavity is formed in silt at the blasting initiation moment, and then the riprap rock body fill the cavity and form a rock tongue, so as to achieve the aim of replacing the silt. The silt is extruded outwards through explosion, and the quantity of the extruded silt is the engineering quantity within the range of the embankment, so that compared with the dredger operation, the engineering quantity of the silt needing to be cleared is greatly reduced, and affected zones of a water area and that under water are greatly reduced at the same time. Materials such as mounting cutting rocks, and the like are firstly filled into the bearing stratum, and then fillers act on the bearing stratum through silt squeezing by blasting, so that the working steps are reduced, the construction cost is greatly shortened. Therefore, the building method has very obvious advantages on the aspects of construction speed, engineering cost and economic benefit.

Description

technical field [0001] The invention relates to a construction technology of urban road embankment engineering, in particular to a construction method of sea reclamation embankment. Background technique [0002] Generally, the construction of urban road embankment works is carried out in the absence of water, and the embankment is generally filled by layered filling and layered rolling. [0003] When the road crosses the seaside shoal or there is a thick silt layer under the water, the embankment is usually constructed by mechanically removing the silt and replacing it. However, this method requires a large excavation area, resulting in a slow construction progress. It is difficult to meet the construction schedule requirements under tight construction schedules. [0004] The commonly used method when building coastal roads in Dalian area to cross the soft ground—excavation and replacement, requires dredgers to remove all the silt in the embankment area that needs to be cle...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E01C3/00E01C3/04E02B3/18F42D1/00
Inventor 庞然
Owner DALIAN MUNICIPAL DESIGN & RES INST
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products