Composite temporary plugging steering repeated fracturing method suitable for shale gas long horizontal well
A long-horizontal well, re-fracturing technology, applied in chemical instruments and methods, earth-moving drilling, wellbore/well components, etc. Take out problems such as difficulty in taking out, to achieve the effect of shortening the construction period, low cost, and improving utilization rate
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0032] This example provides a method suitable for compound temporary plugging and refracturing of long horizontal wells in shale gas, and the horizontal section of the target well is 754m. Its construction includes the following steps:
[0033] 1. Squeeze construction
[0034] Follow 2-4-8-12-14-16m 3 / min ladder displacement, 16-14-12-8-4-2-0m 3 / min step-down discharge rate to target shale gas horizontal wells and inject 300m into old wells 3 Slippery water, wherein, the slick water formula is calculated by weight percentage: 0.08% drag reducer, 0.1% synergist, 0.3% anti-swelling agent, 0.02% bactericide, and the rest is liquid water. Measure the instantaneous stop pump pressure. The pressure-depleted area of the old well is supplemented with energy. When the measured instantaneous pump stop pressure reaches the minimum pump stop pressure of the initial fracturing, the squeeze injection operation is completed; if the measured instantaneous pump stop pressure is lower t...
Embodiment 2
[0043] The horizontal section of the target well is 1480m, and its construction includes the following steps:
[0044] 1. Squeeze construction
[0045] Follow 2-4-8-12-14-16m 3 / min ladder displacement, 16-14-12-8-4-2-0m 3 / min step-down discharge rate to the target shale gas horizontal well old well squeeze injection 3000m 3 Slippery water (its formula is calculated by weight percentage: 0.06% drag reducer, 0.1% synergist, 0.3% anti-swelling agent, 0.01% bactericide, and the rest of the liquid water), measure the instantaneous stop pump pressure, and the old well Energy replenishment is carried out in the pressure depletion area. When the measured instantaneous pump stop pressure reaches the minimum pump stop pressure of the initial fracturing, the squeeze construction is completed; if the measured instantaneous pump stop pressure is lower than the minimum pump stop pressure of the initial fracturing, repeat the above process until the instantaneous pump stop pressure reac...
Embodiment 3
[0054] The horizontal section of the target well is 943m, and its construction includes the following steps:
[0055] 1. Squeeze construction
[0056] Follow 2-4-8-12-14-16m 3 / min ladder displacement, 16-14-12-8-4-2-0m 3 / min step-down discharge rate to the target shale gas horizontal well old well squeeze injection 1500m 3 Slippery water (its formula is calculated by weight percentage: 0.1% drag reducer, 0.1% synergist, 0.2% anti-swelling agent, 0.03% bactericide, and the rest of the liquid preparation water), measure the instantaneous stop pump pressure, the old well Energy replenishment is carried out in the pressure depletion area. When the measured instantaneous pump stop pressure reaches the minimum pump stop pressure of the initial fracturing, the squeeze construction is completed; if the measured instantaneous pump stop pressure is lower than the minimum pump stop pressure of the initial fracturing, repeat the above process until the instantaneous pump stop pressur...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com