Bridge big-height lifting displacement equipment based on vehicle set and construction method thereof
A large-height, vehicle-group technology, which is applied in the fields of installation, construction, dismantling, displacement, and bridge lifting, can solve the problems of bridge side work space, vertical movement only, and long construction period, so as to improve the degree of industrialization and reduce operations The effect of time and high degree of mechanization
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment example 1
[0058] The invention relates to a bridge construction method for lowering the lifting and displacement equipment of train groups, which is mainly used for bridge demolition, lowering the bridge to a safe height for transportation, while meeting the clear height requirements of the transportation passage, or lowering the bridge to a height that can be directly and safely chiseled.
[0059] Such as Figure 6 As shown, during implementation, the large-height lifting and shifting equipment of the bridge based on the vehicle group is first assembled outside the site, and the vehicle group 12 is consigned to the designated position at the bottom of the beam body 15 as a whole, and the upper distribution beam 2 and the bottom of the beam body 15 remain A small section of space is installed to connect the support 1 to ensure that the support members (supporting column 3 on the beam, outer column 7 under the beam, and inner column 8 under the beam) are vertical, and the top surface of t...
Embodiment example 2
[0061] The bridge is prefabricated or cast-in-place at a low elevation, and the bridge is lifted to the design elevation by jacking up before installation, or the low-level prefabricated bridge is safely transported to the designated location, and then falls on the pier after jacking and translation.
[0062] Such as Figure 7 As shown, during implementation, first assemble the conversion connecting beam 6 and the above structure on the vehicle group 12, and place a flattening fixed beam 11 between the conversion continuous beam 6 and the vehicle group 12 in the longitudinal bridge direction, and then install the low-level prefabricated beam The body 15 is safely transported to the vicinity of the designated installation point by the vehicle group 12, and is at a certain distance from the pier column horizontally to ensure that the beam body 15 can be lifted smoothly. At this time, all the load of the beam body acts on the vehicle group 12; Finally, on-site debugging is carrie...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com