New fracturing process suitable for encrypted development of shale gas well
A shale gas well and new process technology, applied in the field of horizontal well fracturing, can solve the problems of difficult breakthrough, high construction cost of single well, limited effect, etc., and achieve the effect of increasing complexity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0031] see Figure 1-4 , a new fracturing process suitable for infill development of shale gas wells, comprising the following steps:
[0032] (1) Data collection, including well logging data and regional in-situ stress prediction results;
[0033] (2) Stress and compressibility analysis. According to the water stress difference in the area where the horizontal well is located, the stress value and the change of the stress field under different fracture spacing conditions are simulated and calculated. The different fracture spacing conditions include 15, 20, 25, 30, and 35m. Other distances are also possible;
[0034] (3) Segment-cluster spacing design. Select an appropriate segment-cluster spacing based on the induced stress difference obtained by simulation calculation in step (2), and minimize the segment-cluster spacing within an appropriate range. The section cluster spacing includes section spacing and cluster spacing, and the selection of cluster spacing should meet t...
Embodiment 2
[0041] The other content of this embodiment is the same as that of Embodiment 1, the difference is that when sand is added continuously, three kinds of particle sizes are combined, and the initial powder pottery-sand ratio is designed to be 3%, so as to ensure the safety of construction and play the role of grinding holes at the same time. The follow-up sand ratio mainly plays the role of filling micro-fractures in the near-wellbore zone, providing favorable conditions for injection in the medium-sand stage; the sand ratio in the medium-sand stage starts at 3-4%, which acts as the main support for the fractures, and the highest sand ratio in this stage is generally designed It is 13-19%; the coarse sand is mainly selected for trailing in the final stage to achieve high conductivity support in the near-wellbore area, and at the same time considering the safety and effectiveness of on-site construction, the sand ratio is designed to be 14-17%.
[0042] The invention relates to a ne...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com