River dredging method
A river channel and silt technology, applied in the field of river channel cleaning, can solve problems such as river channel silting, and achieve the effect of solving silting
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] Such as figure 1 As shown, the present invention provides a river dredging method. The method includes the following steps:
[0041] Step S1: setting the first cofferdam for the section of the river channel, and pumping out the water in the first cofferdam.
[0042] Dams and cofferdams are built in sections of the river course, and the sectioned river courses are set according to the actual situation on site. The first cofferdam is filled with soil, the top width is 6m, and the slope on both sides is 1:1. The earthwork of the first cofferdam is excavated from the muck field and transported to the filling site of the first cofferdam by dump truck. The excavator pushes and rolls the filling into the river until it closes and reaches the design elevation and top width.
[0043] Step S2: Clean up the muck in the river channel.
[0044] Muck includes trash and rocks. Because there are many miscellaneous trees, branches, and domestic garbage on the side slope of the rive...
Embodiment 2
[0048] In yet another embodiment of the present invention, the river channel dredging method in this embodiment is similar to the river channel dredging method in the first embodiment, and the similarities will not be repeated, and only the differences will be introduced.
[0049] In this embodiment, it is disclosed that step S1 specifically includes the following steps:
[0050] Step S11: Excavate the earthwork from the muck field, transport it to the first cofferdam, and then push and roll it into the river channel for filling by the excavator.
[0051] In order to prevent the pressure difference on both sides of the first cofferdam during and after the pumping process, causing the first cofferdam to shift or collapse, wooden piles can be added at the weak points such as the closing point of the first cofferdam to fix the foundation, with a distance of 1m, double Arrange in a quincunx shape, choose the length of the piles according to the actual situation, with a diameter of...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com