Square landscaping and greening construction method
A construction method and square technology, applied in the field of square landscape and greening construction, can solve the problems of high cost, unsatisfactory requirements, waste, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0022] Such as figure 1 As shown, the construction method of a kind of square landscape and greening provided by the present embodiment specifically comprises the following steps:
[0023] Step 1. Obtain the planning area of the square, conduct research according to the planning area, understand the greening requirements of the surrounding residents for the square, and design the planning drawings of the square according to the research results;
[0024] Step 2. Water area setting: Dig a water pool and a rainwater collection pool at the specified place according to the square planning drawings, and set up a green belt near the pool, and set up a rest corridor next to the green belt. Drainage ditch, guardrails are set on the drainage ditch, and music fountain and water curtain projection are set above the center of the pool;
[0025] Step 3. Flood control treatment: install a rainwater treatment system capable of self-purifying rainwater between the rainwater collection tank...
Embodiment 2
[0033] A construction method for square landscape and greening provided in this embodiment specifically includes the following steps:
[0034] Step 1. Obtain the planning area of the square, conduct research according to the planning area, understand the greening requirements of the surrounding residents for the square, and design the planning drawings of the square according to the research results;
[0035] Step 2. Water area setting: Dig a water pool and a rainwater collection pool at the specified place according to the square planning drawings, and set up a green belt near the pool, and set up a rest corridor next to the green belt. Drainage ditch, guardrails are set on the drainage ditch, and music fountain and water curtain projection are set above the center of the pool;
[0036] Step 3. Flood control treatment: install a rainwater treatment system capable of self-purifying rainwater between the rainwater collection tank and the pool; and dig an overflow pipeline lea...
Embodiment 3
[0044] Such as figure 2 As shown, the construction method of a kind of square landscape and greening provided by the present embodiment specifically comprises the following steps:
[0045] Step 1. Obtain the planning area of the square, conduct research according to the planning area, understand the greening requirements of the surrounding residents for the square, and design the planning drawings of the square according to the research results;
[0046]Step 2. Water area setting: Dig a water pool and a rainwater collection pool at the specified place according to the square planning drawings, and set up a green belt near the pool, and set up a rest corridor next to the green belt. Drainage ditch, guardrails are set on the drainage ditch, and music fountain and water curtain projection are set above the center of the pool;
[0047] Step 3. Flood control treatment: install a rainwater treatment system capable of self-purifying rainwater between the rainwater collection tank...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com