Main system device pre-introduction method
A main system and equipment technology, applied in construction, building construction, etc., can solve the problems of delayed dome hoisting, unavailability of special tools, and long introduction of main system equipment, etc., to optimize the construction process, shorten the project cycle, optimize The effect of the total duration
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0090] The present invention will be described in detail below in conjunction with specific embodiments. The following examples will help those skilled in the art to further understand the present invention, but do not limit the present invention in any form. It should be noted that those skilled in the art can make several changes and improvements without departing from the concept of the present invention. These all belong to the protection scope of the present invention.
[0091] The invention relates to a method for installing primary system equipment of a nuclear power plant, in particular to a pre-introduction construction method for quickly completing the installation of main system equipment in place before the reactor building is capped.
[0092] One of the characteristics is to make the cladding module of the pile cavity pool, which is hoisted into the pile cavity before the construction of the pile cavity pool wall, and used as a formwork for the concrete construct...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com