Construction Method of Shallow Buried and Underground Excavated Cross Brace Tunnel

A technology for tunnel construction and shallow burial, which is applied to tunnels, tunnel linings, and earth-moving drilling and mining, etc., can solve the problems of falling blocks from vaults, large leakage of water in tunnels, and large sections of tunnels, and saves money. The effect of rigid cost, improving excavation and excavation efficiency, and shortening construction period

Active Publication Date: 2017-11-07
ZHONGJIAN SUIDAO CONSTR CO LTD
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The invention provides a construction method for shallow-buried tunnels with cross-braces to solve the problem that the current tunnel tunnels have large sections and unique geological characteristics such as rich water, soft top and hard bottom, and large amounts of water seepage in tunnels. , Vault falling blocks and other major safety risk technical issues

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction Method of Shallow Buried and Underground Excavated Cross Brace Tunnel
  • Construction Method of Shallow Buried and Underground Excavated Cross Brace Tunnel
  • Construction Method of Shallow Buried and Underground Excavated Cross Brace Tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0032] The embodiments of the present invention will be described in detail below with reference to the accompanying drawings, but the present invention can be implemented in various ways defined and covered below.

[0033]figure 1 It is a structural block diagram of the construction of a shallow-buried tunnel with cross braces in a preferred embodiment of the present invention; figure 2 It is a structural schematic diagram of a tunnel cross-section in a preferred embodiment of the present invention; image 3 It is a structural schematic view of the tunnel in the preferred embodiment of the present invention along the construction direction.

[0034] Such as figure 1 As shown, the construction method of the shallow-buried cross-brace tunnel of the present embodiment includes the following steps: a, carry out construction preparation, divide the construction area according to the designed tunnel cross-section, and divide the tunnel cross-section horizontally and vertically in...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a shallow-buried subsurface-excavated cross-shaped cross-strut tunnel. The method includes the following steps of conducting construction preparation, conducting measurement and pay-off on a tunnel advanced support and the tunnel contour line according to construction design requirements, conducting advanced geological forecasting through the geophysical prospecting advanced geological forecasting and drilling advanced geological forecasting combined mode, conducting advanced pipe shed grouting and advanced curtain grouting, checking the grouting effect, entering the next procedure if the grouting effect meets the construction requirement, conducting advanced pipe shed and advanced curtain grouting again if the grouting effect does not meet the construction requirement, conducting excavation support construction on construction areas on by one from top to bottom and from left to right, conducting primary support and temporary support sealing and conducting monitoring and measuring after the primary tunnel transverse end face construction is completed, repeatedly executing the steps for the next circulation of construction if the design requirement is met, conducting support strengthening if the design requirement is not met, and regulating excavation parameters to conduct excavation support construction again till the design requirement is met.

Description

technical field [0001] The invention relates to the technical field of tunnel construction, in particular to a construction method for a shallow-buried tunnel with cross braces. Background technique [0002] With the continuous expansion and development of my country's transportation construction, underground excavation projects are developing in a trend of shallow burial depth, poor stratum lithology, abundant groundwater, and complex surrounding environments. Shallow burial and underground excavation have the characteristics of low cost, less demolition, flexibility, no need for too many special equipment, and no interference with ground traffic and the surrounding environment, so it is widely used in various underground underground excavation projects. [0003] In recent years, in order to improve urban traffic conditions and save land, urban rail transit construction has sprung up and developed rapidly. At the same time, in order to select the most favorable operating r...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/00E21D9/10E21D9/12E21D11/10
CPCE21D9/00E21D9/003E21D9/10E21D9/122E21D11/10
Inventor 刘德张家识黄毅翔郑邦友罗伟庭王维邝利军李金求
Owner ZHONGJIAN SUIDAO CONSTR CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products