Method for wastewater pollution control in waste mine shaft
A pollution prevention and mine wastewater technology, applied in mining equipment, earth drilling, mining equipment, etc., can solve the problems of personnel death and property, underground material transportation, water pollution, etc., to avoid personnel death and property loss accidents, The effect of solving water leakage accidents and solving pollution problems
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0017] Such as figure 1 As shown, the mine waste rock is mixed with the gelling agent (cement + fly ash) according to the mass ratio of 7 / 3, and mixed with water to make a slurry with a solid-liquid mass ratio of 3 / 1; the above slurry is transported to In the mine roadway (1) in the rock mass (6), use it as a material to build an airtight isolation solidification body (2) with a thickness of 5m and an interval of 50m along the mine roadway (1) from the inside to the outside. A compartment (3) is formed therebetween, and the accumulated water in the goaf (5) and the compartment (3) is plugged and sealed, thereby completing the prevention and control of waste water pollution in the abandoned mine roadway (1).
Embodiment 2
[0019] Mix mine tailings with gelling agent (cement + asphalt) at a mass ratio of 5 / 2, and mix with water to make a slurry with a solid-to-liquid ratio of 4 / 1; transport the above slurry to the rock mass (6) In the mine roadway (1) inside, use it as a material to build an airtight isolation solidification body (2) with a thickness of 20m and an interval of 100m along the mine roadway (1) from the inside to the outside, forming compartments between the airtight isolation solidification bodies (3), the stagnant water in the goaf (5) and the compartment (3) is plugged and sealed, and the prevention and control of waste water pollution in the abandoned mine roadway (1) is completed.
Embodiment 3
[0021] Mix mine solid waste (waste rock + smelting slag) with gelling agent (cement + fly ash + asphalt) at a mass ratio of 2 / 1, and mix with water to make a slurry with a solid-to-liquid ratio of 5 / 2 The above-mentioned slurry is transported in the mine roadway (1) in the rock mass (6), and it is 50m to build thickness along the mine roadway (1) from the inside to the outside with it, and the airtight isolation solidification body ( 2), a compartment (3) is formed between the sealed and isolated solidified bodies, the accumulated water in the goaf (5) and the compartment (3) is plugged and sealed, and the prevention and control of waste water pollution in the abandoned mine roadway (1) is completed.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com