Method for grid and province two-stage real-time generation schedule coordinative optimization under generalized tie line mode

A technology for real-time power generation planning, coordination and optimization, applied in computing, instrumentation, data processing applications, etc., can solve problems such as shortages, and achieve the effects of strong adaptability, low computing intensity, and improved intelligence and decision-making capabilities.

Active Publication Date: 2014-07-23
NARI TECH CO LTD +1
View PDF1 Cites 21 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] In order to solve the deficiencies of the existing technology, the purpose of the present invention is to provide a two-level grid-province real-time power generation plan coordination and optimization method under the generalized tie-line mode, which can solve the lack of effective adjustment of the prior day output plan of the provincial dispatching unit and the provincial power generation plan in the prior art. Adjusting the output plan of the directly subordinate network regulation and control unit to ensure the coordinated operation of the real-time plan and operation of the network provincial regulation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for grid and province two-stage real-time generation schedule coordinative optimization under generalized tie line mode
  • Method for grid and province two-stage real-time generation schedule coordinative optimization under generalized tie line mode
  • Method for grid and province two-stage real-time generation schedule coordinative optimization under generalized tie line mode

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0031] The present invention will be specifically introduced below in conjunction with the accompanying drawings and specific embodiments.

[0032] refer to figure 1 As shown, under the generalized tie-line mode of the present invention, the network-province two-level real-time power generation plan coordination optimization method, in order to distinguish the responsibilities of the network-province regulation and control unit, and make the network-province regulation real-time plan coordinated operation, the provincial regulation generalized connection line plan and the provincial regulation The definition of the generalized tie-line plan on the directly affiliated network dispatching side, as long as the real-time plans of the regional power grid and the provincial power grid meet their respective generalized tie-line constraints, the coordinated operation of the real-time plan of the grid-provincial dispatching can be guaranteed. In the process of preparing the real-time p...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method for grid and province two-stage real-time generation schedule coordinative optimization under a generalized tie line mode. The method is characterized by comprising the following steps that firstly, province scheduling generalized tie line plans are obtained through calculation; secondly, a grid scheduling department issues all the province scheduling generalized tie line plans to corresponding province scheduling departments, and the grid scheduling department obtains a generalized tie line plan of each grid scheduling side directly under the province scheduling through calculation; thirdly, sensitivity information is calculated; fourthly, all kinds of information are read; fifthly, the generalized tie line soft constraint of the corresponding province is added, soft constraint cost is added to a conventional optimization object at the same time, then a province-stage power grid mathematic model is formed, the generalized tie line soft constraint of each grid scheduling side directly under the province scheduling is added, soft constraint cost is added to the conventional optimization target at the same time, then a first area power grid mathematic model is formed, the whole-grid grid scheduling side generalized tie line constraint is added on the basis of the first mathematic model, and a second area power grid mathematic model is formed; sixthly, optimization calculation is started. The method for grid and province two-stage real-time generation schedule coordinative optimization under the generalized tie line mode has the advantages that calculation intensity is low and adaptability is high and is suitable for popularization and application in China scheduling mechanisms of all scales.

Description

technical field [0001] The invention relates to a method for coordinating and optimizing power generation plans, in particular to a method for coordinating and optimizing power generation plans in real time at two levels of grid and province under a generalized tie-line mode. The invention belongs to the technical field of power system scheduling automation. Background technique [0002] At present, with the gradual advancement and implementation of smart grid construction, according to the next day's electricity demand forecast, considering various constraints such as system balance constraints, unit operation constraints, and power grid operation constraints, optimize the preparation of the 96-point unit combination plan and output plan for the next day The degree of practicality of the power generation planning function has been gradually improved. The day-ahead scheduling plan supports three scheduling modes: energy-saving dispatching, power market, and three-public disp...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/04G06Q50/06
CPCY04S10/50
Inventor 张彦涛丁恰曹斌高宗和戴则梅涂孟夫吴炳祥朱敏健
Owner NARI TECH CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products