Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Method for constructing from central area to periphery of ultra-large type underground engineering

An underground engineering and construction method technology, applied in water conservancy projects, underwater structures, infrastructure engineering, etc., can solve the problems of construction progress, difficulty, increased risk, high support system cost, and expensive construction enclosure cost, etc., to achieve The effect of improving construction safety and reliability, saving project cost, and saving construction period

Active Publication Date: 2015-04-08
HANGZHOU NANLIAN BASE FOUND ENG
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Due to the high depth and ultra-large plane scale of underground engineering construction, the traditional method of using enclosure walls combined with internal vertical and horizontal multi-layer support systems makes the construction enclosure cost expensive, and the construction progress, difficulty, and risks are all increased, especially In soft soil areas, it is almost impossible to set up internal supports without internal support. However, due to the large scale of the plane, the cost of the support system is very high

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Method for constructing from central area to periphery of ultra-large type underground engineering
  • Method for constructing from central area to periphery of ultra-large type underground engineering
  • Method for constructing from central area to periphery of ultra-large type underground engineering

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0036] Such as Figure 1-9 As shown, a construction method in which the central area of ​​a super-large underground project is combined with the surrounding areas, the specific construction steps are as follows:

[0037] 1), construction foundation pit enclosure wall 6, engineering pile 7, support and trestle support pile 8;

[0038] 2) grading of the upper soil around the foundation pit or excavation of soil nailing wall enclosure, control deformation anchor rods under construction and support conditions, and pouring top beams;

[0039] 3) The central area is sloped and excavated to the bottom, and the basement floor 1 and the third underground floor 2 floor 4 structure of the central area are completed;

[0040] 4) Combining the surrounding conditions, the upward construction completes the structure of the second floor 3 underground in the central area, and at the same time, the beam slab 5 or beam structure of the second underground floor in the surrounding area is complete...

Embodiment 2

[0053] Such as Figure 10-18 As shown, a construction method in which the central area of ​​a super-large underground project is first combined with the surrounding area, the surrounding support system is a temporary surrounding support 11 supported by reinforced concrete or steel, and the specific construction steps are as follows:

[0054] 2.1), step 1), 2) and 3) construction in embodiment 1, step 4) in construction central area underground two-story 3 floor slab structure, construction enclosing beam and peripheral support 11 simultaneously, make peripheral support 11 and underground two Floor slabs 4 are connected as a whole, and the setting height of peripheral support 11 should enable excavator and earth truck to drive normally to carry out excavation operation; then follow steps 5), 6) to carry out construction;

[0055] 2.2) In step 7), the trestle 9 is removed, and the basement floor 1 in the surrounding area and the floor structure of the third underground floor 2 a...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method for constructing from the central area to the periphery of an ultra-large type underground engineering, comprising the following steps of: firstly, sloping and excavating to the bottom of a pit in a middle area of the underground engineering; then, directly constructing a bottom plate of a basement in the middle area, and upwards constructing to finish a floorslab structure of the underground engineering; and establishing a peripheral bracing system by using the finished floorslab structure in the middle area as a bracing point to finally finish the construction for the peripheral basement. By utilizing the characteristic of large plane size of the underground engineering, the middle area is sufficiently utilized to slope for construction firstly, the underground engineering in the middle area is constructed upwards, and a peripheral area is provided with a permanent beam slab or temporary bracing as a bracing by taking a top beam slab of the underground engineering in the constructed middle area as the bracing point, so that the defects of causing difficulty in excavating and transporting soil in the peripheral area and controlling the stress direction of the peripheral diagonal bracing, affecting the engineering progress and improving the construction difficulty due to the adoption of the traditional central island construction method is foundationally overcome.

Description

technical field [0001] The invention relates to an underground engineering construction method, in particular to an underground engineering construction method suitable for large plane scale and deep excavation. Background technique [0002] With the large-scale development of basic construction, urban land is becoming more and more tense, and it is developing underground. Exploitation and utilization of underground space is an inevitable trend of future development. Underground projects such as ultra-large and high-depth basements, underground shopping malls, and parking lots have emerged rapidly. Due to the high depth and ultra-large plane scale of underground engineering construction, the traditional method of using enclosure walls combined with internal vertical and horizontal multi-layer support systems makes the construction enclosure cost expensive, and the construction progress, difficulty, and risks are all increased, especially In soft soil areas, it is almost imp...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/045
Inventor 严平
Owner HANGZHOU NANLIAN BASE FOUND ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products