[0044] A construction method of non-extracting soil composite grouting pile, comprising the following steps:
[0045] (1) Construction of the first pile:
[0046] (1) Move the machine into place: move the equipment and place the drill pipe on the set pile position;
[0047] (2) Spinning sinking: Spinning and sinking the drill pipe to the set depth;
[0048] (3) Rotary pulling up: Rotate the drill pipe, inject the curing agent into the soil at the same time, and rotate to the set height;
[0049] (4) Repeat steps (2) and (3) until the first pile meets the set requirements;
[0050] (2) Construction of the second pile:
[0051] (1) In place: place the outer pipe of the equipment on the first pile that has been constructed;
[0052] (2) Immersed tube: sink the outer tube to the set depth;
[0053] (3) Pouring molding: Lift the internal rammer, pour the pile body or lower the prefabricated pile body, when lowering the prefabricated pile body, fill the outer peripheral gap of ...
Embodiment 2
[0072] A construction method of non-soil-extracting composite pipe piles. The method for constructing the second pile is to use external force to sink the prefabricated pile to a set depth. When the second pile is a hollow pile, the hollow pile is sealed up and down, and the cavity part is segmented. Or cast reinforced concrete throughout. In method B of the construction of the second pile, the method of sealing the upper and lower sides of the hollow pile is: use prefabricated pile boots or iron plates for the bottom cover, and plugs or iron plates for the top; Pouring reinforced concrete in sections or in whole sections. All the other are with embodiment 1.
Embodiment 3
[0074] A construction method of non-soil-extracting composite bottom-expanding cast-in-situ piles, the method for constructing the second pile is tube sinking and bottom-expanding piles, and the rest are the same as in Embodiment 1.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com