Dislocation installation method of corrugated steel web
A corrugated steel web, staggered installation technology, applied in the erection/assembly of bridges, bridges, buildings, etc., can solve the problems of long joint welding time, affecting the installation of steel bars and templates, and many processes crossing, so as to improve efficiency and uniform distribution. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 2
[0029] The specific construction steps of installing the steel web in step 2 of the above-mentioned embodiment are:
[0030] 1) Use the electric hoist 4 on the construction truss truck 3 to lift the corrugated steel web of the n+1 segment, and slide along the track for a short distance to the front end of the installed corrugated steel web of the n segment, see figure 1 ;
[0031] 2) Temporarily connect the corrugated steel web of the n+1 segment and the corrugated steel web of the n segment with bolts for preliminary positioning;
[0032] 3) Use the electric hoist 4 to adjust the elevation of the corrugated steel web of the n+1 segment, and after meeting the design requirements, start the welding of the corrugated steel web of the n segment and the corrugated steel web of the n+1 segment for permanent connection .
[0033] In step 2, the reason why the corrugated steel web of the n+1 segment is lifted by the electric hoist 4 on the construction truss truck 3 after 24 hours ...
Embodiment 3
[0035] The installation process of installing steel bars and corrugated pipes includes adjusting templates, binding top and bottom steel bars, positioning prestressed corrugated pipes, and installing top and bottom templates. The above steps are the same as the existing construction methods, and will not be described in detail here.
[0036] This corrugated steel web dislocation installation method makes there be no intersection between the various processes, and at the same time avoids the problem of workers’ idleness during the equal strength period and the shortage of personnel in the next section of construction (the three processes of steel bars, formwork, and steel webs are carried out at the same time) , to achieve the effect of uniform distribution of human resources on the time axis, improve efficiency, and save 10-12 hours per cycle.
[0037] The effect comparison of each process before and after using the corrugated steel web dislocation installation method is as fol...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com