Geotextile bag shock absorption and vibration isolation building foundation, and construction method and application thereof
A geotechnical bag and foundation technology, which is applied in the direction of basic structure engineering, construction, protection devices, etc., can solve the problems of poor vertical shock absorption effect and high price, and achieve good shock absorption and isolation effect, good effect and resource saving Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0024] Example 1: A geotechnical bag shock-absorbing and seismic-isolation building foundation
[0025] Excavate a 1.2m×1.2m×1.2m foundation pit on the ground floor directly below the building pillars (50cm×50cm), arrange 40cm×40cm geotechnical bags in a criss-cross pattern and lay 8 layers, each layer is pressed by a roller compactor The gaps between the solid and geotechnical bags are filled with excavated soil to form a geotechnical bag pier foundation, and three layers of geotechnical bags are laid under the load-bearing wall of the building, arranged in a crisscross manner and compacted to form a geotechnical bag strip foundation. Lay 3 layers of geotechnical bags on the entire foundation surface of the building, arrange them in a criss-cross pattern and compact them to form a raft-shaped foundation of geotechnical bags, and pour a layer of reinforced concrete floor on the top surface of the raft-shaped foundation.
Embodiment 2
[0026] Embodiment 2: A construction method for a geotechnical bag shock-absorbing and seismic-isolation building foundation, its construction steps are as follows:
[0027] A. First put the foundation soil excavated from the construction site into a 40cm×40cm woven bag, and tie the bag mouth well to form a geotechnical bag for use;
[0028] B. Excavate a foundation pit with a depth of 1.2m×1.2m×1.2m under the building column according to the load on the upper part of the building and the foundation conditions, and compact the surface of the foundation pit with a rolling machine;
[0029] C. Place the geotechnical bags of step A layer by layer in the foundation pit in a criss-cross arrangement, roll them layer by layer with a rolling machine, and fill the gaps between the geotechnical bags with the excavated foundation soil;
[0030] D. Construct layer by layer according to the method of step C, and lay 8 layers of geotechnical bags to form a geotechnical bag pier-shaped founda...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com