A construction method for highway reconstruction and expansion for reaming bridge sections

A technology of expressways and construction methods, applied in bridge construction, bridges, bridge maintenance, etc., can solve problems such as difficulty in ensuring high-speed driving of vehicles, inability to solve vehicle safety problems, increase project cost, etc., to achieve driving safety and comfort guarantee, The effect of smooth stiffness transition and saving engineering investment

Active Publication Date: 2022-08-09
SHANDONG TRAFFIC PLANNING DESIGN INST
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] ① Close one-way traffic, only guarantee one-way traffic
It is difficult to ensure the high-speed driving of vehicles by using temporary steel temporary bridges in Baotong Bridge. The Baotong Bridge adopts concrete or steel box girder bridges, and it is difficult to reuse after the Baotong Bridge is completed. Although this kind of Baotong guarantees the normal operation of traffic, it greatly increases the project cost.
[0007] The main reason for the many problems and shortcomings of the current protection scheme is that it cannot solve the problem of the safety of vehicles driving on roads with different rigidities to form an overall protection section with the same rigidity as the newly-built reaming part on the outside and the original subgrade road surface on the inside.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction method for highway reconstruction and expansion for reaming bridge sections
  • A construction method for highway reconstruction and expansion for reaming bridge sections
  • A construction method for highway reconstruction and expansion for reaming bridge sections

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0082] For the convenience of description, the coordinate system is now defined as figure 1 As shown, the left-right direction is the horizontal direction, the front-rear direction is the vertical direction, and the up-down direction is the vertical direction.

[0083] In order to facilitate the understanding of this method, the initial subgrade structure before the construction of the reaming bridge section is described as follows: figure 1 As shown, the initial roadbed structure includes a reamed bridge section and a widened road section that has been widened. The reaming bridge section includes the original roadbed 111 and the original bridge body 112 . The widened road section includes a left new subgrade 121 and a right new subgrade 122. The left new subgrade 121 is composed of the left original subgrade 1211 and the left widened subgrade 1212. The original subgrade 1221 on the right and the subgrade 1222 in the width on the right are composed.

[0084] A construction ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
thicknessaaaaaaaaaa
Login to View More

Abstract

The invention discloses a construction method for highway reconstruction and expansion aimed at reaming bridge sections, and relates to the technical field of highway reconstruction and expansion. The construction method utilizes part of the original roadbed and pavement, and splices it with the newly-built bridges. During the reconstruction and expansion construction, the roadbed and bridges are jointly maintained, which not only saves the project investment, but also achieves the requirements of smooth and smooth expressways during the construction period. At the same time, a transition block is set between the original subgrade and the newly-built bridge, so that the transition of stiffness of the spliced ​​section is smooth. After splicing, the stiffness of the overall section changes due to the gradual change of the stiffness of the concrete transition block, and the stiffness of the subgrade and the bridge transitions smoothly. can be guaranteed. The method solves the problem of maintaining the passage of the reaming bridge section on the premise of basically not increasing the project cost.

Description

technical field [0001] The invention relates to the technical field of highway reconstruction and expansion, in particular to a construction method for highway reconstruction and expansion aimed at reaming bridge sections. Background technique [0002] With the rapid development of my country's economy and society, the traffic volume continues to increase, and the demand for high-speed traffic continues to increase. Expressway reconstruction and expansion projects have gradually become the mainstream of expressway construction. In order not to affect the normal traffic operation as much as possible during the construction of the reconstruction and expansion project, it is particularly important to keep the traffic intact. With the increasing demand for local production roads, in the reconstruction and expansion of bridges across local production roads on expressways, the number of bridges that need to be rebuilt (that is, roads and bridges need to be widened at the same time...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E01D21/00E01D24/00E01C7/18E01C11/02
CPCE01D21/00E01D22/00E01C7/18E01C11/02Y02A30/60
Inventor 于坤王同卫李炙彬柳磊翟聪李士宏左咏鹏姜美文邓煜王海山闫见华仲浩然冉衠孙伟荣
Owner SHANDONG TRAFFIC PLANNING DESIGN INST
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products