Bedding mortar protection device for prefabricated bent cap and prefabricated stand column and construction method thereof
A protective device and construction method technology, which is applied to bridges, bridge parts, bridge construction, etc., can solve the problems of grout overflow, etc., and achieve the effect of improving construction efficiency and tight connection
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0038] see Figure 1 to Figure 3 , which is a structural schematic diagram of a prefabricated cover beam and prefabricated column anti-seating protection device 100 provided in an embodiment of the present invention. Component 20. Wherein, a plurality of protective pieces 10 are connected to each other to form an accommodating cavity 11 for accommodating the prefabricated column 40 , and a plurality of locking assemblies 20 are circumferentially distributed on a side of the plurality of protective pieces 10 away from the accommodating cavity 11 .
[0039] A plurality of protective pieces 10 can prevent the sitting grout from overflowing from the connection between the prefabricated column 40 and the prefabricated cover beam during the lowering process of the prefabricated cover beam. On the one hand, the locking assembly 20 can support the corresponding protective piece 10, improving the bearing capacity of the protective piece 10, thereby avoiding the pressure damage of the ...
Embodiment 2
[0055] see Figure 7 , which is a schematic flowchart of a construction method for prefabricated cover beams and prefabricated columns to be grouted according to the second embodiment of the present invention. The construction method of the prefabricated cover beam and the prefabricated column is used to bond the connecting surfaces of the prefabricated column and the prefabricated cover beam together through the sitting grout. The construction method of the prefabricated cover beam and prefabricated column sitting slurry for example includes:
[0056] Step S10, setting the sitting slurry protection device 100 on the top of the prefabricated column 40, so that the upper end of the sitting slurry protection device 100 protrudes from the top of the prefabricated column 40 to form a sitting area 50 at the top of the prefabricated column 40;
[0057] Step S20, installing the second connecting piece 30, and adjusting the position of the protective piece 10;
[0058] Step S30, adj...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com