Construction method of integrally pulling and laying turnout
A construction method and turnout technology, which is applied to roads, tracks, laying tracks, etc., can solve the problems of inconvenient turnout lateral movement and increased labor force, and achieve the effects of improving construction quality, saving labor force, and ensuring normal operation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0036] Embodiment 1: A construction method for integrally spreading a turnout, comprising the following steps:
[0037] Step 1, construction preparation: complete the pre-laying of the turnout, the welding flaw detection of the rail inside the turnout, and the combined engineering and electricity adjustment; polish the turnout, store the ballast under the pre-laid turnout; block the line.
[0038] Step 2, cutting the rail: cutting the rail with a cutting machine, so that the rail to be cut is separated from the original rail.
[0039] Step 3, remove the rails and sleepers: use an excavator to transport the cut rails and the sleepers at the bottom of the rails, and transport the rails and sleepers out of the site.
[0040] Step 4, track ballasting: After the line is removed and the old materials are transported out of the construction site, use an excavator to clean the ballast bed. The depth of the track bed is not less than 10cm, and the ballast is placed between the two line...
Embodiment 2
[0048] Embodiment 2: A construction method for integrally spreading a turnout, comprising the following steps:
[0049] Step 1, construction preparation: complete the pre-laying of the turnout, the welding flaw detection of the rail inside the turnout, and the combined engineering and electricity adjustment; polish the turnout, store the ballast under the pre-laid turnout; block the line.
[0050] Step 2, cutting the rail: cutting the rail with a cutting machine, so that the rail to be cut is separated from the original rail.
[0051] Step 3, remove the rails and sleepers: use an excavator to transport the cut rails and the sleepers at the bottom of the rails, and transport the rails and sleepers out of the site.
[0052] Step 4, track ballasting: After the line is removed and the old materials are transported out of the construction site, use an excavator to clean the ballast bed. The depth of the track bed is not less than 10cm, and the ballast is placed between the two line...
Embodiment 3
[0061] A construction method for the integral laying of a turnout, comprising the following steps:
[0062] Step 1, construction preparation: complete the pre-laying of the turnout, the welding flaw detection of the rail inside the turnout, and the combined engineering and electricity adjustment; polish the turnout, store the ballast under the pre-laid turnout; block the line.
[0063] Step 2, cutting the rail: cutting the rail with a cutting machine, so that the rail to be cut is separated from the original rail.
[0064] Step 3, remove the rails and sleepers: use an excavator to transport the cut rails and the sleepers at the bottom of the rails, and transport the rails and sleepers out of the site.
[0065] Step 4, track ballasting: After the line is removed and the old materials are transported out of the construction site, use an excavator to clean the ballast bed. The depth of the track bed is not less than 10cm, and the ballast is placed between the two lines.
[0066]...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com