A construction method and technology for pumping and draining water, which can be used in foundation structure engineering, sheet pile walls, buildings, etc., to solve problems such as difficulty in dissipation, displacement of pile position, horizontal and vertical displacement of soil, and achieve overall stability improvement and stiffness. improved effect

Active Publication Date: 2020-04-10
沙焕焕
View PDF2 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] If the construction of the existing cement-soil piles is in soft soil, due to the high water level of the soft soil base and the high water content of the soil, it is easy to generate large super-pore water pressure during pile foundation construction and it is difficult to dissipate
This problem will cause the horizontal and vertical displacement of the soil, and even cause the pile body to float and the pile position to shift, affecting the quality and stability of the foundation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0018] A construction method of a stiff composite pile based on pumping, draining and dewatering comprises the following steps:

[0019] (1) 20 days before the construction of the stiffened composite pile, in the soft soil layer around the pile site of the stiffened composite pile to be constructed, a plurality of tube wells and plastic drainage boards arranged at intervals are set up for pumping and drainage operations, so that the groundwater level is lowered and the soil The water content of the body is reduced, the density is increased, the upper soft soil is hardened and dense, the depth of the tube well is 15 meters, and it is located 20 meters outside the pile position, and the depth of the plastic drainage board is 10 meters, with a spacing of 6 meters;

[0020] (2) 10 days before the construction of the cement-soil pile, carry out the construction of the bulk pile on the pile site, and drive the bulk materials such as gravel and pebble into the soft soil;

[0021] (3)...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a stiff composite pile based on pumping and drainage water reduction. The construction method comprises the steps that (1) a plurality of tube wells and plastic drainage plates are arranged for pumping and drainage operation in a peripheral soft soil layer of a pile position of the to-be-constructed stiff composite pile, the underground water levelis lowered, the water content of a soil body is decreased, density is improved, and upper soft soil is hardened and dense; (2) construction of a discrete pile is carried out on the pile position; (3)stirring and high-pressure air injection, powder injection or guniting operation are carried out in the discrete pile, a cement soil pile is constructed, pumping and drainage operation is continuouslycarried out through the surrounding tube wells, injected gases, powder or slurry moves towards the tube wells, and powder or slurry is easily absorbed by the soil body; and (4) a rigid core pile is constructed in the cement soil pile. According to the construction method, the construction effect in soft soil is good, a pile body is dense, strength is high, soil around the pile is stable, and integral stability of a foundation is good.

Description

technical field [0001] The invention relates to a construction method of a stiff composite pile based on pumping, draining and dewatering. Background technique [0002] If the construction of the existing cement-soil piles is in soft soil, due to the high water level of the soft soil base and the high water content of the soil, it is easy to generate large super-pore water pressure during pile foundation construction and it is difficult to dissipate. This problem will cause the horizontal and vertical displacement of the soil, and even cause the pile body to float and the pile position to shift, which will affect the quality and stability of the foundation. Contents of the invention [0003] The purpose of the present invention is to provide a construction method suitable for cement-soil piles in soft soil, adding tube wells, plastic drainage boards and bulk materials, forming exhaust and drainage channels in soft soil, and extruding when constructing rigid core piles The...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D5/46
CPCE02D5/46
Inventor 魏东海沙焕焕邓亚光
Owner 沙焕焕
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products