Substation switch room reserved pre-buried rear construction method
A technology for switch rooms and substations, applied in substation rooms, industrial buildings, buildings, etc., can solve the problems of expensive formwork, affecting appearance, axis offset and elevation error, etc., to achieve the effect of convenient construction, saving formwork and manpower
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0022] 1. Construction: Basic construction preparation:
[0023] Before pouring concrete, it is required to clean the floor, and weld the ground flat iron firmly according to the design drawings.
[0024] 2. Technical requirements for base concrete before spreading:
[0025] Before spreading the material, it is required that the base concrete should be vibrated and compacted, leveled, and the concrete surface should be free of floating water. The spreading material is emery wear-resistant material.
[0026] Initial dewatering and squeegeeing;
[0027] About 2 hours after the concrete is poured (the time is different in different weather conditions), when people step on the concrete surface and the subsidence is not obvious, an aluminum alloy ruler can be used to scrape it. There are two purposes for scraping:
[0028] a) Make the concrete surface preliminary level;
[0029] b) Concentrate the laitance on the concrete surface; remove the concentrated laitance with a rubber ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com