A method for installation and construction of special-shaped leg column support

A construction method and technology of leg columns, which are applied in construction, building structure, and processing of building materials, etc., can solve problems such as weak force, and achieve high bearing capacity and safe and stable support

Active Publication Date: 2016-05-11
CHINA CONSTR SIXTH ENG BUREAU CIVILENG +1
View PDF13 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The oblique legs of this patent are used to support the No. 0 block, and the connection between the left row of pier columns and the right row of pier columns and the cap is connected by pre-embedded bolts, which is easy to form a weak point of force

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A method for installation and construction of special-shaped leg column support
  • A method for installation and construction of special-shaped leg column support

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0018] (1) Install 5 layers of bottom stress reinforcement on the cap cushion at the top of the pile foundation of the cap, and install multiple sets of support piers on the cap cushion at the same time, and the multiple sets of support piers and the multi-layer bottom are stressed The intersecting parts of the steel bars are welded and connected; the supporting pier includes four supporting columns, the cross section of the area surrounded by the four supporting columns is rectangular, and four supporting column connecting beams are installed on the top of the four supporting columns. The column connection beam of the supporting pier is installed on the top of the reinforced steel bar at the bottom of the 5th floor. (2) Install the portal-type steel-stiff main frame 1 arranged vertically on the connecting beam of the supporting pier, and then use the bottom layer arranged horizontally between the lower part and the middle part of the adjacent main frame 1 The connecting beam ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an irregular-shaped leg column support installation and construction method. The method comprises the following steps that (1) multiple layers of bottom load-bearing rebars are installed on a bearing platform bed course at the top end of a pile foundation of a bearing platform, meanwhile, multiple sets of supporting piers are installed on the bearing platform bed course, and the supporting piers are welded to the intersections of the bottom load-bearing rebars; (2) a bearing platform door type stiff main framework is fixed to each set of supporting piers in the vertical direction, and then the lower portions and the middle portions of the adjacent main frameworks are fixedly connected through bottom-layer connecting beams and the middle load-bearing rebars, wherein the bottom-layer connecting beams and the middle load-bearing rebars are arranged in the horizontal direction; (3) concrete is poured in the spacing between the bearing platform bed course and the upper portions of the middle load-bearing rebars; (4) the tops of the adjacent main frameworks are fixedly connected through top-layer connecting beams arranged in the horizontal direction; (5) multiple layers of top load-bearing rebars are fixedly connected to the top-layer connecting beams; (6) supports are installed on the main frameworks. By the adoption of the method, the whole stress system having enough bearing capacity is formed.

Description

technical field [0001] The invention relates to a support construction method, in particular to a special-shaped leg post support installation construction method. Background technique [0002] The special-shaped leg column used to support the shaftless large-tonnage ferris wheel must have sufficient bearing capacity and a stable landing support point. The Chinese patent with the application number CN201310583286.6 discloses a "double-row four-slant-leg steel structure portal pier", which specifically relates to a double-row four-slant-leg steel structure portal pier. It includes block No. 0 and a steel cover beam. The two ends of the bottom of the steel cover beam are respectively connected with a left row of pier columns and a right row of pier columns. Right cap, the left row of pier columns includes the first left pier column and the second left pier column, the tops of the first left pier column and the second left pier column intersect at the bottom end of the steel c...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04G21/14E04B1/36
Inventor 王丽梅孙旭平余沛
Owner CHINA CONSTR SIXTH ENG BUREAU CIVILENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products