Construction method, system and special components of a ventilating roof system
A roofing system and breathable technology, applied in the direction of roofing, roof covering, buildings, etc., can solve the problems of roof waterproofing system failure, roof concrete structure deterioration, large surface, etc., to reduce construction and maintenance costs, reduce use and maintenance. Cost, ease of construction and maintenance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0044] Embodiment 1: see figure 1 , the construction method of a kind of air-permeable roof system provided by the present invention, it comprises the following steps:
[0045] (1) A waterproof layer 2 is set above the roof concrete structure beam slab and the water-facing surface 1 built on the roof wall to block the moisture from the outdoors from entering the roof wall;
[0046] (2) A moisture-absorbing and releasing hydrophobic filling layer 3 having the function and effect of absorbing and releasing moisture and draining water is arranged above the waterproof layer 2, and the moisture-absorbing and releasing hydrophobic filling layer 3 is composed of materials with air permeability and water absorption , the material is one of clay ceramsite, gravel, hydrophobic and breathable bricks, or granular debris made of bricks and concrete waste. There are gaps and capillary channels inside the material to absorb and store the materials that reach the roof and walls. The moisture...
Embodiment 2
[0051] Example 2: see figure 2 , Figure 6A and Figure 6B , the construction method of the air-permeable roof system provided by this embodiment is basically the same as that of Embodiment 1, and it includes the following steps:
[0052] (1) Install a waterproof layer 2 above the water-facing surface 1 of the roof concrete structure beam slab and the roof concrete structure beam slab and the roof wall to block the moisture from the outdoors from entering the roof wall middle;
[0053] (2) A moisture absorption and release hydrophobic filling layer 3 is arranged above the waterproof layer 2, and the moisture absorption and release hydrophobic filling layer 3 is composed of materials with air permeability and water absorption;
[0054] (3) A foam insulation layer 4 is set between the waterproof layer 2 and the moisture absorption and release hydrophobic filling layer 3, and the foam insulation layer 4 is formed by laying a foam insulation board 41 provided with a plurality ...
Embodiment 3
[0060] Embodiment 3: see image 3 , Figure 6A , Figure 6B and Figure 7 , the construction method of the air-permeable roof system provided by the present invention is basically the same as Embodiment 1, and it includes the following steps:
[0061] (1) Install a waterproof layer 2 above the water-facing surface 1 of the roof concrete structure beam slab and the roof concrete structure beam slab and the masonry roof wall to prevent moisture from outdoors from entering the roof wall middle;
[0062] (2) A moisture absorption and release hydrophobic filling layer 3 is arranged above the waterproof layer 2, and the moisture absorption and release hydrophobic filling layer 3 is composed of materials with air permeability and water absorption;
[0063](3) A foam insulation layer 4 is set between the waterproof layer 2 and the moisture absorption and release hydrophobic filling layer 3, and the foam insulation layer 4 is formed by laying a foam insulation board 41 provided wit...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com