Method for monitoring movement of dam body of five-level tailings pond
A technology for displacement monitoring and tailings ponds, applied in the direction of measuring devices, instruments, etc., can solve the problems of no tailings pond dam displacement monitoring facilities
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 2
[0048] (1) Layout of working base point and displacement observation point
[0049] ① Working base point
[0050] The purpose of embedding the working base point is to facilitate the observation of each displacement observation point. The selected point should be in a relatively stable place with good visibility conditions, and two points should be buried for mutual checking; the coordinate results of the working base point are in the mine Based on the control network, it is measured by making a lower-level displacement monitoring network;
[0051] ②Displacement observation point
[0052] The displacement observation point is buried in a position that can reflect the deformation characteristics, and at the same time, along the initial dam crest, dam foot and downstream of the tailings pond, a total of 5 sections are set, and the distance between each section is 50 meters;
[0053] Others are the same as above.
Embodiment 3
[0055] (1) Layout of working base point and displacement observation point
[0056] ① Working base point
[0057] The purpose of embedding the working base point is to facilitate the observation of each displacement observation point. The selected point should be in a relatively stable place with good visibility conditions, and 8 points should be buried for mutual checking; the coordinate results of the working base point are in the mine Based on the control network, it is measured by making a lower-level displacement monitoring network;
[0058] ②Displacement observation point
[0059] The displacement observation point is buried in a position that can reflect the deformation characteristics, and at the same time, it is set at 7 sections along the initial dam crest, dam foot and downstream of the tailings pond, and the distance between each section is 120 meters;
[0060] Others are the same as above.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com