Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Drainage construction method of counter-slope tunnel boring machine (TBM) tunneling tunnel

A construction method and tunnel technology, applied in drainage, earthwork drilling, safety devices, etc., can solve problems such as no water to pump, sediment accumulation, serious problems, etc., and achieve the effect of reducing pumping distance, saving costs, and reducing investment

Active Publication Date: 2019-11-15
CHINA RAILWAY TUNNEL GROUP CO LTD +1
View PDF6 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

During the excavation construction process, the tunnel water gushing is mainly tunnel water seepage. In addition to the groundwater itself, the water quality also includes rocks, mud, and shotcrete rebound, which will cause sediment to accumulate in the water pump and affect the work of the water pump. Moreover, the existing drainage The inrush water volume was not considered during the construction, the drainage capacity could not meet the drainage demand, and the configuration of drainage pipes and water pumps was unreasonably optimized, resulting in severe water accumulation in some parts and no water to pump in some parts
The various problems faced in the above-mentioned drainage construction will cause water accumulation in the tunnel during the excavation construction process.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Drainage construction method of counter-slope tunnel boring machine (TBM) tunneling tunnel
  • Drainage construction method of counter-slope tunnel boring machine (TBM) tunneling tunnel
  • Drainage construction method of counter-slope tunnel boring machine (TBM) tunneling tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0033] Embodiment 1: For the anti-slope TBM excavation tunnel drainage construction method of a certain project, see the TBM construction section figure 1 , using a Φ8.02m open hard rock roadheader for construction.

[0034] The construction section is located in the downstream of reservoir 1. The construction section of the main tunnel is from No. 3 branch tunnel 101 to 1942m downstream of the extension section 2 of the main tunnel, with a total length of 18.275km. (100m), main engine assembly hole 4 (80m), first deployment hole 5 (200m), first starting hole 6 (25m), TBM first tunneling section 7 (8310m), upstream connection section 8 (1500m), Maintenance hole 9 (60m), second entry hole 10 (240m), downstream connecting section 11 (1500m), second starting hole 12 (25m) and TBM second tunneling section 13 (6235m).

[0035] The horizontal distance of No. 3 branch tunnel 101 is 3872m, the slope distance is 3885m, and the comprehensive slope is 8.18%. In order to solve the probl...

Embodiment 2

[0133] Example 2: Drainage scheme of the branch hole, on the basis of Example 1, drain water through the branch hole.

[0134] Drainage scheme of 2# branch tunnel: add a 300mm drainage pipeline (No. 3) on the basis of the original two 300mm drainage pipelines (No. 1 and No. 2 pipelines, which can only be used after partial treatment) in 2# branch tunnel , No. 1 and No. 2 pipelines are pumped out of the cave with two-stage drainage, and No. 3 is pumped to the top with one pump and directly pumped out of the cave. Pipeline No. 1 is equipped with a MD280-215 water pump at the bottom of the cave to discharge to the original 2# water tank in the 2# branch cave, and a MD280-172 water pump is installed in the original 2# water tank to pump out the cave; No. 2 pipeline is in One set of MD250-151 water pump is installed at the bottom of the cave to pump and discharge to the original 3# water tank of the 2# branch cave, and one set of MD280-172 water pump is installed at the original 3#...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a drainage construction method of a counter-slope tunnel boring machine (TBM) tunneling tunnel. The drainage construction method of the counter-slope TBM tunneling tunnel aimsto solve the technical problem of water accumulation in the construction of the counter-slope TBM tunneling tunnel. The drainage construction method of the counter-slope TBM tunneling tunnel comprisesthe steps that normal water inflow and maximum water inflow of the tunnel are predicted; water tanks are arranged at intervals in the tunnel, the number and volume of the water tanks are determined based on the maximum water inflow of the tunnel, the slope of a counter-slope and the length of the tunnel; drainage pipelines are arranged between the adjacent water tanks, pump stations are arrangedat each water tank, each pump station is provided with a plurality of water pumps, water in the tunnel is gradually drained to the water tanks through the water pumps, and the water in the tunnel is drained in stages. The water drawing distance is reduced, the investment is reduced, inner diameters and material of the drainage pipelines and types of the water pumps are rationally selected, the requirements of drainage can be met while the cost is saved to the greatest extent. By optimizing the configuration of drainage equipment, the tunnel counter-slope drainage construction efficiency is improved, and the counter-slope drainage construction cost is reduced.

Description

technical field [0001] The invention relates to the technical field of tunnel drainage construction, in particular to a drainage construction method for reverse-slope TBM excavation tunnels. Background technique [0002] TBM (Tunnel Boring Machine) is a tunnel boring machine, which can realize the construction of long tunnels with complex geographical features and landforms that are difficult to realize by traditional drilling and blasting methods, and can realize parallel and continuous operations in construction procedures such as excavation, support, and slag discharge. [0003] During the tunnel construction process, the tunnel excavation often has a certain slope. When the tunnel excavation slope is along the slope, natural drainage can be used to achieve the purpose of drainage. However, when the tunnel excavation slope is reverse slope, the geological conditions are complex, the reverse slope tunnel distance is long, the slope is large, the buried depth is large, the ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E21F16/02
CPCE21F16/02
Inventor 胡新朋黄力洪开荣黎峰黄大为靳纪国郑清君王雅宜罗于恺李小莉文仁玉
Owner CHINA RAILWAY TUNNEL GROUP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products