Project cost modification method and system
A technology of project cost and project plan, applied in the field of project cost, can solve the problems of reducing the accuracy of project cost, producing changes, cumbersome operation, etc., and achieve the effect of improving the summary of materials and improving efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0049] In one embodiment, as figure 1 As shown, the present invention discloses a method for modifying engineering cost, which specifically includes the following steps:
[0050] S10: If the price change message is obtained, the price change material identifier and the change price data are obtained from the price change message.
[0051] In this embodiment, the price change message refers to a message that the price of construction materials has changed. The change material ID is the name used to refer to the material for which the price has changed. The changed price data refers to the price change data corresponding to the material whose price has changed. The changed price data may be the specific figure after the price is changed, or the extent of the price change.
[0052]Specifically, after the price change message is obtained, the price change material identifier and the change price data are obtained from the price change message.
[0053] S20: Using a preset proj...
Embodiment 2
[0102] In one embodiment, a project cost modification system is provided, and the project cost modification system corresponds to the project cost modification method in the above-mentioned embodiments one by one. Such as Figure 6 As shown, the project cost revision system includes a change message acquisition module 10 , a data matching module 20 , a marking module 30 and a price adjustment module 40 . The detailed description of each functional module is as follows:
[0103] The change message acquisition module 10 is used to obtain the price change material identification and change price data from the price change message if the price change message is obtained;
[0104] The data matching module 20 is used to match the engineering material data sheet from the engineering file data using the preset engineering cost template, and the engineering material data sheet includes the engineering material identification;
[0105] The marking module 30 is used to use the price ch...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com