Open cut construction method of underground station
A technology for underground stations and construction methods, applied in artificial islands, water conservancy projects, underwater structures, etc., can solve the problems of slow construction progress, occupying urban ground space, and small scope of application, and achieve the effect of meeting travel needs.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0031] to complete figure 1 , figure 2 The construction of the underground station A shown in the figure, and the opening to traffic of the track line B before the completion of the construction of the underground station, is an open-cut construction method for the underground station. combine Figure 3a —As shown in 3c, including the following steps:
[0032] The first step is to carry out grading excavation on the ground of the proposed underground station, which is the same as the first step grading excavation of the traditional full cut and cover.
[0033] The second step, such as Figure 3a As shown, the prefabricated left and right frame segments are hoisted into the excavation pit and assembled along the length direction of the underground station to form the left and right symmetrically arranged guide tunnels in the lower layer of the station, and then track laying, power supply and communication are completed, so that the station has traffic conditions. The left...
Embodiment 2
[0039] to complete figure 1 , figure 2 The construction of the underground station A shown in the figure, and the opening to traffic of the track line B before the completion of the construction of the underground station, is an open-cut construction method for the underground station. combine Figure 3a —As shown in 3c, including the following steps:
[0040] The first step is to carry out grading excavation on the ground of the proposed underground station, which is the same as the first step grading excavation of the traditional full cut and cover.
[0041] The second step, such as Figure 4a As shown, the prefabricated left and right frame segments are hoisted into the excavation pit, assembled and fixed along the length direction of the underground station to form a left and right symmetrical arrangement of the station's lower guide tunnel, and then the track laying, power supply and communication are completed, so that the station has a traffic conditions. The left...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com