Distribution network fault recovery method based on A* algorithm and fireworks algorithm
A technology of distribution network fault and fireworks algorithm, applied in electrical components, circuit devices, AC network circuits, etc., can solve problems such as poor calculation efficiency, long calculation time, and difficulty in ensuring recovery effects.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0110] According to this embodiment figure 1 The flowchart operates.
[0111] The distribution network diagram used in this embodiment is as follows figure 2 shown. The distribution network has a total of 33 nodes, the active load is 3715kW, the reactive load is 2300kVar, and node 1 is a slack node, and the per unit value is used for calculation (the voltage reference value is 12.66kV, and the power reference value is 10MVA). In order to increase the scale of the system, there are switches on each branch, that is, the number of switches is equal to the number of branches, that is, the distribution network has 33 nodes, 32 branches, and 3 contact switch branches. See the appendix for basic system data and DG information.
[0112] The specific operation steps of the recovery method in this embodiment are as follows:
[0113] (1) When there is a fault near node 5, after the section switches 4-5 and 5-6 are disconnected to isolate the fault, the original data of the distribut...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com