Novel wall drilling equipment for construction site
A construction site and drilling equipment technology, applied in stone processing equipment, working accessories, manufacturing tools, etc., can solve the problems of time-consuming and labor-intensive drilling, inability to drill accurately, high risk of drilling process, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0037] A new type of wall drilling equipment for construction sites, such as Figure 1-6 As shown, it includes a bottom plate 1, a first guide rail 2, a first guide sleeve 3, a screw rod 5, a pressure block 6, a support plate 7, a first slide rail 8, a first slider 9, a first fixing plate 10, a first The motor 11 and the drill bit 12, the upper middle part of the base plate 1 is installed with the first guide rail 2 by welding, the first guide rail 2 is slidably connected with the first guide sleeve 3, and the lower right side of the first guide sleeve 3 has a threaded hole 4, A screw 5 is placed in the threaded hole 4, and the screw 5 cooperates with the threaded hole 4. The left end of the screw 5 is rotatably connected with the first pressure block 6, and the front side of the first guide sleeve 3 is installed with a support plate 7 by welding. The first slide rail 8 is installed on the upper left side by welding, the first slide rail 8 is slidably connected with the first ...
Embodiment 2
[0039] A new type of wall drilling equipment for construction sites, such as Figure 1-6 As shown, it includes a bottom plate 1, a first guide rail 2, a first guide sleeve 3, a screw rod 5, a pressure block 6, a support plate 7, a first slide rail 8, a first slider 9, a first fixing plate 10, a first The motor 11 and the drill bit 12, the upper middle part of the base plate 1 is installed with the first guide rail 2 by welding, the first guide rail 2 is slidably connected with the first guide sleeve 3, and the lower right side of the first guide sleeve 3 has a threaded hole 4, A screw 5 is placed in the threaded hole 4, and the screw 5 cooperates with the threaded hole 4. The left end of the screw 5 is rotatably connected with the first pressure block 6, and the front side of the first guide sleeve 3 is installed with a support plate 7 by welding. The first slide rail 8 is installed on the upper left side by welding, the first slide rail 8 is slidably connected with the first ...
Embodiment 3
[0042] A new type of wall drilling equipment for construction sites, such as Figure 1-6 As shown, it includes a bottom plate 1, a first guide rail 2, a first guide sleeve 3, a screw rod 5, a pressure block 6, a support plate 7, a first slide rail 8, a first slider 9, a first fixing plate 10, a first The motor 11 and the drill bit 12, the upper middle part of the base plate 1 is installed with the first guide rail 2 by welding, the first guide rail 2 is slidably connected with the first guide sleeve 3, and the lower right side of the first guide sleeve 3 has a threaded hole 4, A screw 5 is placed in the threaded hole 4, and the screw 5 cooperates with the threaded hole 4. The left end of the screw 5 is rotatably connected with the first pressure block 6, and the front side of the first guide sleeve 3 is installed with a support plate 7 by welding. The first slide rail 8 is installed on the upper left side by welding, the first slide rail 8 is slidably connected with the first ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com