Acidizing depressurization and increasing injection process with non-moving strings for water injection wells

A process method and water injection well technology, which is applied in earthwork drilling, wellbore/well components, production fluid, etc., can solve problems such as increased water injection pressure of water injection wells, insufficient oil well energy, and reduced injection volume, etc., and achieve relief results. The effect of reducing dirt, saving construction operation costs, and extending the validity period

Active Publication Date: 2016-06-15
BC P INC CHINA NAT PETROLEUM CORP +1
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] However, during the production process of water injection wells, due to the incompatibility of injected water and formation water, scale will slowly form in the wellbore of water injection wells and near the wellbore, causing the water injection pressure of water injection wells to gradually increase, the injection volume to decrease, and finally to high pressure in water injection wells Insufficient injection, and the corresponding oil well energy is insufficient

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0036] As the best implementation mode of the present invention, the present invention discloses a process method for acidifying depressurization and increasing injection with a non-moving string for water injection wells, the steps of which are as follows:

[0037] a. In terms of volume ratio, take 0.3-3 parts of weak acid acidification solution and mix with 99.7-97 parts of injection water;

[0038] b. Inject the mixed solution into the water inlet pipeline by drip injection;

[0039] c. When the set injection volume is reached and the pressure of the water injection well drops to 90% of the water injection pressure before construction, stop injecting the mixed solution;

[0040] Described weak acid acidification liquid is: by weight percentage, its component is:

[0041] Acid solution: 10~30%;

[0042] Stabilizer: 2~8%;

[0043] Corrosion inhibitor: 1~5%;

[0044] Surfactant: 6.5~17%;

[0045] The balance is distilled water.

[0046] The acid solution is one or more o...

Embodiment 2

[0048] Embodiment 2-field application example of the present invention

[0049] Step 1: Transport the acidizing fluid material and supporting equipment of the immovable string to the designated location corresponding to the injection well on site;

[0050] Step 2: Add the acidizing fluid material of the fixed column into the weak acid acidizing fluid skid;

[0051] Step 3: Shut down the water injection wells for 0.5 hours, then open the backwash well gates at the wellheads of the water injection wells for backwashing, and close all the six-way wellhead gates of all the water injection wells after the well flushing water reaches a well volume.

[0052] Step 4: Connect the skid-mounted device of the weak acid acidification liquid to the six-way wellhead (inlet pipeline) of the injection well.

[0053]Step 5: Adjust the six-way wellhead valve of the water injection well to the normal water injection state.

[0054] Step 6: Turn on the switch of the skid-mounted device for the w...

Embodiment 3

[0057] Embodiment 3-another field application example of the present invention

[0058] Step 1: Transport the acidizing fluid material and supporting equipment of the immovable string to the designated location corresponding to the injection well on site;

[0059] Step 2: Shut down the injection wells for 0.5 hours, use a 350-type well washing vehicle to backwash the injection wells, and close all the six-way wellhead gates of all injection wells after the well washing water reaches a well volume.

[0060] Step 3: Add the non-moving column acidizing fluid material into the weak acid acidizing fluid skid, and connect the weak acid acidizing fluid skid to the six-way wellhead (inlet pipeline) of the injection well.

[0061] Step 4: Adjust the six-way wellhead valve of the water injection well to the normal water injection state.

[0062] Step 5: Turn on the switch of the skid-mounted device for the weak acid acidification solution, adjust the ratio of the switch of the skid-mou...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method for acidizing depressurization and increasing injection with a non-moving pipe column for water injection wells. The steps are as follows: a. In terms of volume ratio, take 0.3-3 parts of weak acid acidizing liquid and mix with 99.7-97 parts of injection water; b. Inject the mixed solution into the water inlet pipeline through drip injection; c. Stop injecting the mixed solution when the set injection volume is reached and the pressure of the water injection well drops to 90% of the water injection pressure before construction; the weak Acidification liquid is: by weight percentage, its components are: acid liquid: 10-30%; stabilizer: 2-8%; corrosion inhibitor: 1-5%; surfactant: 6.5-17%; The volume is distilled water. This method expands the radius of acidizing plugging removal of water injection wells, alleviates scaling near the wellbore of water injection wells, and prolongs the validity period of water injection wells; realizes continuous mixing and acidification of immobile strings, and simplifies the construction process; synchronous water injection acidification does not affect the normal operation of water wells Production.

Description

technical field [0001] The present invention relates to the technical field of pressure-reducing and increasing-injection process methods for water injection wells, in particular to a method for acidizing and increasing injection in sandstone reservoirs in low-permeability oilfields, with large acidizing and plugging-removing radius, increased validity period, and continuous mixing without moving pipe strings. Acidification and water injection are carried out simultaneously without affecting the depressurization and increase injection process of normal production. Background technique [0002] At present, during the development of low-permeability oilfields, the oil recovery is enhanced by water injection as the formation energy decays. For example, the Chinese patent document with the publication number CN202250005U and the publication date of May 30, 2012 discloses a water injection well pressure-reducing and injection-increasing device. , used in oilfield water injection ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21B43/22E21B43/20
Inventor 任雁鹏蒋文学李勇徐洋范杰马托王兴建何举涛安全成付振银周然武龙汪小宇金娜韩婧婧孟庆聪荆建春王玉功
Owner BC P INC CHINA NAT PETROLEUM CORP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products