Spud shoe priority docking process
A pile boot and process technology, applied in the field of the pile boot priority docking process, can solve problems such as easy collapse, and achieve the effects of fast construction speed, good quality and good construction stability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0019] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0020] Taking the spud shoe priority docking process of a 90-meter offshore platform as an example, it includes the following steps:
[0021] A. Tooling production and installation in place: Through the overall consideration of the process, it is first necessary to make the spud shoe tooling 1 and install the spud shoe tooling 1 at the four spud shoe positions in the dock;
[0022] B. Complete loading of the main hull: carry out the loading of the main hull of the platform according to the process sequence of the loading network diagram, and install the local supports of the main hull in the area of the four spud shoes at the same time;
[0023] C. Docking of the first section of pile leg 4 with spud shoe 3: After the main hull of all platforms is loaded, and all components and equipment in the enclosure area are installed, the docking work of the fir...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com