Mounting method of tower crane boom and auxiliary mounting pull rod applied by tower crane boom
A boom and tie rod technology, which is applied in the field of tower crane boom installation, can solve the problems of inability to provide an assembly site, heavy quality, and inapplicability of large lifting equipment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0043] The method for installing the boom of a tower crane of the present invention uses auxiliary installation pull rods to install the boom in sections. Please refer to figure 1 , the tower crane 100 includes an auxiliary installation tie rod 10 , a tower body 20 , a balance arm 30 , a balance arm tie rod 40 , a boom 50 , a boom tie rod 60 and a brace 70 . The top of the tower body 20 is provided with a revolving platform 22, and the ends of the balance arm 30, the brace 70 and the boom 50 are installed on the revolving platform 22 respectively. It can be understood that, according to different models, the slewing platform 22 may only include an upper support, and may further include a slewing tower suitable for setting a driver's cab. In the model in which the slewing platform 22 only includes the upper support, the balance arm 30 , the brace 70 and the jib 50 are respectively connected to the upper support. In the machine model in which the slewing platform 22 includes a...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com